Heat substation Ziduri Mosi: hours of below-standard hot water, 2025–2026
Sector 2
42Reconstructed hours with a notice of hot water below standard · in 2025
250 national threshold: 250 hours per year and contract · local threshold: total waiver
Calendar dates with at least one captured notice: 17
The notices concern at least part of the substation’s area. They do not measure the temperature in a flat and do not establish that compensation is owed.
| Year | Hot water below standard, hours | Dates with a notice | Heating below standard, hours | Hot water off, hours | Heating off, hours |
|---|---|---|---|---|---|
| 2025 | 42 | 17 | 213 | 642 | 17 |
| 2026* | 218 | 28 | 237 | 358 | 92 |
* The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.
Last captured notice (original, in Romanian) · 2026-10-22 10:51
Lipsa parametri pentru livrare apă caldă de consum
• Ale Câmpul Moşilor - bl. 2; 1 • Şos Colentina - bl. 4A; 3; 4; 5 • Str Ziduri Moşi - bl. 6
Streets named in the notices
- Ale Câmpul Moşilor
- Şos Colentina
- Str Ziduri Moşi
Outages and their causes, on this substation’s page in “Why your hot water is off”