Saved or movedRO

Ordinance 41/2025 · lists published September–November 2025

Romania put 21 schools on its recovery plan’s reserve list, on a promise. At least four were not ready by the deadline

In August 2025 an emergency ordinance made recovery-plan (PNRR) projects that were at most 30% built continue only with government approval. Each ministry then proposed, project by project, what stayed in the plan and what moved to other money. Education put 21 unfinished green schools on the plan’s reserve list, on the beneficiaries’ sworn word that they would be done by 31 August 2026. Environment moved 451 water and waste projects named in an annex, plus 28 more contracts, to the Environment Fund. Look up your commune in the published lists.

Try:

Twenty-one schools on the reserve list, on their word#

In September 2025 Romania’s Education Ministry had 21 green-school projects, new or renovated, at most 30% built. Their value, per the ministry’s annex: 658.8 m lei. The government did not cut them. It put them on a PNRR reserve list, on the strength of each beneficiary’s sworn statement that the works would be finished by 31 August 2026.

13announced as finished: reception, inauguration or a completion notice
4still building after the deadline, or blocked at last report
4with no public word on their state at the deadline

The memorandum said all 21 had already issued the order to start works. In Cața, Brașov county, the site was empty and blocked in May 2026. In Florești the announced end of the works contract, March 2027, was past 31 August; on 5 September work still remained. In Iași the new wings were inaugurated in September and October, and at „Mihai Eminescu” the works were not done in the first week of term.

At the last PNRR revision, adopted on 5 August 2026, the green-school targets were set at 18,289 m² renovated and 32,764 m² built. The areas planned in the 12 projects that had passed 30% exceed those targets on their own: 22,633 m² and 34,723 m², if received on time. For the targets, the 21 reserve schools were not needed.

Who pays for what was not finished: in May an Education Ministry official said works not received by the end of August can no longer be claimed from the Commission, and money already reimbursed “stays with the beneficiaries”. The mayor of Florești said the commune will pay for the remaining works. What the Commission accepts will be known after it assesses the final payment request, filed on 30 September 2026.

BeneficiaryCountyContractWhat is known in November 2026
CațaBrașov14.4 m leiblocked On 3 May 2026 the site was empty, blocked over land permits. Its 216 pupils study in a 100-year-old building rented from the church. [1] [2]
SânpetruBrașov47.8 m leistill building after deadline New school on weak ground, with 418 piles. On 21 August 2026 the contractor was asking to extend the contract to 30 October. The local council extended the schedule by 70 days (decision 91/2026). [1] [2]
BodBrașov35.8 m leistill building after deadline New primary school. The town hall’s September 2026 photos show the building still under construction. [1]
FloreștiCluj22.9 m leistill building after deadline Extension of the „Dumitru Tăutan” high school. On 5 September 2026 the works were about 95% done. The works contract’s announced end was past 31 August; the mayor says the commune pays for the rest. [1]
VolovățSuceava36.2 m leiunknown New school wing. Works resumed in March 2026; its state at the deadline is unconfirmed. [1] [2]
Frătăuții VechiSuceava27.7 m leiunknown Renovation of the „Ion Pintilie” school in Măneuți. No public information on the works. [1]
SaravaleTimiș15.3 m leiunknown New school. Furniture and equipment were tendered in October 2026; nothing on the building itself. [1]
Peștișu MicHunedoara11.4 m leiunknown New school in Nandru village. Works began in May 2025; no information from 2026. [1]
Consiliul Județean TimișTimiș74.4 m leiannounced finished New building for the inclusive-education school in Giroc, for 250 pupils. Finished at the end of August 2026. [1] [2]
Valea LupuluiIași51.0 m leiannounced finished New school with 19 classrooms. Received at the end of August 2026, it stood empty at the start of term while permits were pending. On 5 November the head teacher announced the first classes would move in. [1] [2] [3]
PantelimonIlfov43.3 m leiannounced finished New middle school. 77% done on 29 July 2026; completion announced on 30 September. [1] [2]
IașiIași43.3 m leiannounced finished Three high schools. The new wings at „Miron Costin” and „Mihai Eminescu” were inaugurated in September and October 2026, after the deadline; nothing confirms „Garabet Ibrăileanu”. [1] [2] [3]
CojascaDâmbovița42.3 m leiannounced finished New school in Iazu village for about 700 pupils. Inaugurated on 20 August 2026. [1] [2]
DumbrăvițaTimiș39.7 m leiannounced finished New school. Still under construction on 28 July; completion announced on 20 August 2026. [1] [2]
FrumușaniCălărași34.4 m leiannounced finished New school, grades 0–8. The town hall announced the project finished on 28 August 2026. [1] [2]
BufteaIlfov31.2 m leiannounced finished New green school of over 3,500 m². Works received on 25 August 2026. [1] [2]
BorceaCălărași27.8 m leiannounced finished New school for 216 pupils. The town hall announced the project finished in August 2026. [1]
Moșnița NouăTimiș25.3 m leiannounced finished New high school with 13 classrooms. Works received on 6 August 2026. [1] [2]
VoitinelSuceava12.9 m leiannounced finished New wing at the middle school. The town hall announced the project finished in August 2026. [1]
DrăgeștiBihor12.3 m leiannounced finished New school, inaugurated on 6 September 2026. [1] [2]
Alba IuliaAlba9.5 m leiannounced finished Renovation of the „Ion Agârbiceanu” school. Works received on 21 August 2026. [1]

Status of each school from public sources checked on 23 November 2026: town hall notices, local press, tenders. “Finished” means a source reports the reception, inauguration or completion of the project; no source yet confirms, for all of them, that pupils are taught there.

The 30% rule#

Emergency Ordinance 41/2025 sorted PNRR projects by how much of them had been built. The threshold was 30% of the works, certified by contractors’ progress statements.

0%30%100% No tender launched: contract denounced (art. 3)Preparation, no works: suspended (art. 4) Up to 30%: stopped unless the government approves (art. 5) Over 30% and done by 31.08.2026: continues (art. 6)

Projects under the threshold did not stop automatically. Each ministry sent the government a memorandum listing the projects it wanted to continue, with PNRR money or other money. A project under the threshold that was missing from its ministry’s memorandum was suspended or denounced.

19.08.2025The government adopts Ordinance 41/2025: projects under 30% stop unless a memorandum decides otherwise.
18.09.2025The government approves 11 memoranda, among them those of Education, Health and Transport.
16.10.2025The Environment memorandum: water and waste projects move to the Environment Fund.
13.11.2025The Development memorandum: 5,372 projects worth 26 bn lei stay in the PNRR; 4.18 bn lei come from the state budget.
December 2025An emergency ordinance hands the Environment Fund over 500 projects, with a ceiling of 4.34 bn lei.
31.08.2026The PNRR’s final deadline for milestones and targets.

Water and waste left the PNRR#

The Environment Ministry took 479 contracts, worth 5.01 bn lei, out of the PNRR and handed them to the Environment Fund. They are water and sewerage networks, waste drop-off centres and manure platforms. The fund takes over the part not yet built: 3.93 bn lei.

451projects named in the published annex, in 377 communes, towns and cities, plus associations and county councils
3.93 bn leileft to build, now with Environment Fund money
143.9 m leimissing for water and sewerage at the time of the decision, “to be identified”

For water and sewerage the memorandum put the need at 1.91 bn lei from the fund’s budget, up to 2028. 1.76 bn lei was available. The difference, 143.9 m lei, “is to be identified and secured within available budget resources”. The waste projects are paid from the money Romania earns by auctioning carbon emission allowances.

The water, sewerage and waste-collection projects are tied directly to cases the European Commission has already opened against Romania: untreated urban waste water (case 2018/2109, referred to the EU Court of Justice in 2024) and missed recycling targets (case 2024/2136). The memorandum calls the projects “critical” to those cases.

The 30% threshold is not uniform here. Drop-off centres were 3% to 70% built, recycling islands under 36%, urban centres 0 to 40%. Besides the projects taken over, the memorandum names 21 eligible recycling plants, worth 408.2 m lei, for which no money existed; their list was not published.

Water and waste projects moved from the PNRR to the Environment Fund, per the Environment Ministry memorandum approved on 16 October 2025. Values include VAT. * Not listed by name in the published annex.
InvestmentContractsValue, m leiLeft to build, m lei
Water and sewerage, places over 2,000 population equivalent812,016.51,530.1
Sewerage, places under 2,000 population equivalent25331.5271.5
Connecting low-income households (water operators)*14128.5106.2
Drop-off recycling centres2181,128.9887.3
Digital recycling islands60415.5321.5
Integrated collection centres, large towns10330.4272.6
Recycling plants (companies)*14421.8348.6
Manure and compostable farm waste57238.1195.0
Total4795,011.33,932.9

Where the projects are

Values from the published annex, summed by county. Iași, Timiș and Prahova have the largest sums.

Iași360 m
Timiș278 m
Prahova232 m
Ilfov219 m
Suceava214 m
Argeș170 m
Mureș168 m
Constanța162 m
Galați161 m
Arad158 m
Giurgiu157 m
Maramureș147 m

The largest contracts

BeneficiaryCountyWhatm lei
Comuna JoițaGiurgiuWater and sewerage, places over 2,000 population equivalent108.3
Comuna MăgureleIlfovWater and sewerage, places over 2,000 population equivalent89.5
Asociația Regională pentru Dezvoltarea Infrastructurii din Bazinul Hidrografic Someș–TisaSălajWater and sewerage, places over 2,000 population equivalent80.4
Comuna JilavaIlfovWater and sewerage, places over 2,000 population equivalent67.7
Adi TorontalTimișWater and sewerage, places over 2,000 population equivalent60.3
Comuna VoineștiIașiWater and sewerage, places over 2,000 population equivalent58.8

The December 2025 ordinance raised the list to “over 500 projects” and the ceiling to 4.34 bn lei. Its annex was not published with the announcement; this page uses the list of 16 October 2025.

Universities and the Development projects#

The other education projects under 30% belong to universities: 35 contracts for student halls, canteens and recreation spaces, worth 1,156 m lei, and 5 regional vocational campuses, worth 676 m lei. All went onto the same list, under the same article 5.

The Development Ministry published only the list of contracts it kept: 6,078 rows, worth 26.98 bn lei including VAT. Among them are 1362 for building renovation, 4595 from the Local Fund and 119 for crèches. Payments, commune by commune, are in the PNRR payments ledger.

What was not published#

No ministry published its list of projects that were cut. So a commune that does not appear here has not necessarily had its project saved.

  • Education announced 83 contracts denounced, worth 1.8 bn lei, and 16 suspended, worth 906 m lei. The annex naming them was not published.
  • Health took whole hospitals out of the PNRR; some moved to the Health Programme 2021–2027. The lists reported in the press differ from each other, and the ministry did not publish an official list.
  • Transport moved projects worth 62 bn lei to the Transport Programme. The memorandum’s published annex is a scan of the projects kept, without those moved.
  • Development published the projects it kept, not those it stopped.

What Romania is paid for all this is being decided in Brussels now. In its preliminary assessment in November 2026, the European Commission found 69 of the 75 milestones and targets in payment request 5, worth €2.67 bn, met. The money for the other six may be cut.

How this page was made#

The page reads three official lists as published. The Environment annex names 451 projects with county and value; their count per investment matches the memorandum. The annex values add up to 4.56 bn lei, against 4.46 bn lei in the memorandum text for the same projects; the page uses the memorandum totals, and each project’s own row uses the annex value.

The Education annex has 9,625 contracts and no county. A contract is tied to a commune only when the name is unique in Romania or the text names the county; the rest show up in search marked “same name in several counties”. Subtotals by article match the annex, except for three kept investments (school minibuses, university digitalisation, school managers’ training), where extraction misses 0.6% of the sum.

The Development list is the one of 14 November 2025, read and tied to communes for the PNRR payments ledger. Communes are identified by their SIRUTA code; population is from 2022.