Promised green: traffic-light priority for Bucharest's buses and trams, delivered in 2008–2009, contracted again in 2019. The city's study: it has never worked

A late bus should be able to ask the next junction for green, and the light should give it. Bucharest's "smart" traffic-light system was delivered with that function in 2008–2009, for 300 vehicles. In 2019 the city's Streets Administration contracted a separate licence for it again: 154,985.73 lei excluding VAT. The feasibility study approved by the city council in June 2026 says public-transport priority "has never worked", and puts it in the budget once more: 509,243.16 lei for a new module, plus 263,608.22 lei for the link to vehicle data.

  1. 2008–2009DeliveredThe original traffic-light system, installed turnkey, included tracking for 300 vehicles, linked to the lights. That part has no separate price.Passed acceptance tests, then went unused (mobility-plan report, 2015)
  2. 2019Contracted again154,985.73 lei excl. VAT, line 3 of contract ASB 02/2019, with 12 days to implement in the annex.The published documents show the price, not payment or acceptance
  3. 2026Budgeted again509,243.16 lei for a "BUS/TRAM priority module" and 263,608.22 lei for an interface to vehicle data.An estimate in the approved study, not a contract

#What should happen at the traffic light

Signal priority means a bus, trolleybus or tram approaching a junction gets its green a little earlier, or keeps it a few seconds longer. For that, information has to pass through five steps. If one is missing, the light learns nothing about the vehicle.

✕1The vehicle knowswhere it is✕2It sends a priorityrequest✕3The traffic-lightsystem receives itand decides✕4The light changesphase5The vehicle crosseson green✕1The vehicle knows where itis✕2It sends a priorityrequest✕3The traffic-light systemreceives it and decides✕4The light changes phase5The vehicle crosses ongreen

A World Bank report from April 2021 describes three ways Bucharest's traffic-light software, UTOPIA, can receive requests: directly from the system that tracks the fleet, through a standard vehicle-data feed (SIRI), or through detectors in the road. It calls the first "the most reliable"; the third cannot favour particular vehicles, such as late ones.

What is at stake is speed. The study for the first stage of the modernisation, also approved in June 2026, notes that only 12 of the 66 urban bus lines average more than 15 km/h on weekdays.

The stage I study (council decision 242/2026) on bus-line speeds (Romanian).
The stage I study (council decision 242/2026) on bus-line speeds (Romanian). PDF, page 34

#Seventeen years, four documents, five moments

Each official document below is about the same function: how it was delivered and contracted, and how the authors explain why it did not reach regular service. Pick a year to see which link in the chain the document describes and exactly what its page says.

✕1The vehicle knowswhere it is✕2It sends a priorityrequest✕3The traffic-lightsystem receives itand decides✕4The light changesphase5The vehicle crosseson green✕1The vehicle knows where itis✕2It sends a priorityrequest✕3The traffic-light systemreceives it and decides✕4The light changes phase5The vehicle crosses ongreen

2008–2009 Delivered and tested

Feasibility study approved in 2026, page 12; 2015 mobility-plan report, page 18

In 2008–2009 a UTI–Swarco consortium installed Bucharest's traffic-management system on a turnkey basis. The study's list includes "Sistem PTM FLASH cu integrarea a 300 vehicule": the fleet-tracking system, linked to the traffic lights, integrating 300 vehicles.

The report for the Sustainable Urban Mobility Plan describes how it was meant to work: 300 vehicles with on-board units, positions sent by TETRA radio, and priority requested locally, over Wi-Fi, at every junction in the system. A late bus could ask for its green to come earlier or last longer. Both functions, priority and following the bus with a camera, "were successfully tested at the project's acceptance".

The study approved by council decision 243/2026, on the 2008–2009 system (Romanian).
The study approved by council decision 243/2026, on the 2008–2009 system (Romanian). PDF, page 12
Mobility-plan report (2015): local priority passed acceptance tests (Romanian).
Mobility-plan report (2015): local priority passed acceptance tests (Romanian). PDF, page 18

The chain shows what each document describes, not an independent technical diagnosis. The causes are the documents' authors'.

#What the city contracted in 2019

On 4 January 2019 the Bucharest Streets Administration (ASB), the city body that contracts traffic-light work, signed contract 02 with SWARCO Traffic Romania to upgrade the traffic centre's software: 2,690,724.50 lei excluding VAT. The price annex has seven lines. Line 3 is "Licența modul Prioritate Transport Public", a licence for the public-transport priority module: 154,985.73 lei.

No.Annex line (original Romanian)Lei, excl. VATDays to implement
1Update pentru toate modulele UTOPIA, la ultima versiune disponibilă794,301.8712
2Update pentru toate modulele OMNIA la ultima versiune disponibilă794,301.8712
3Licența modul Prioritate Transport Public154,985.7312
4Licența pentru servicii Gateway interfețe externe77,492.8712
5Licența modul UTOPIA VISSIM116,239.3012
6Extindere MISTIC cu noi funcționalități: Strategy Manager Event Dynamic; Management484,330.4112
7Licența modul City Dashboard269,072.4512
Contract total, excl. VAT2,690,724.50
The signed annex to contract ASB 02/2019: line 3 is the public-transport priority licence.
The signed annex to contract ASB 02/2019: line 3 is the public-transport priority licence. PDF, page 8

All seven lines carry the same schedule in the annex: 10 days to deliver, 12 days to implement. The contract does not name the FLASH product against the licence; whether the 2019 licence is the FLASH module described in the 2026 study can only be confirmed from the technical offer and the acceptance record, which are not part of the published contract.

Another line, a "Gateway" licence for external interfaces, has its own price. Its name does not prove it covered the link to the public-transport fleet system. The public documents show contracted prices, not payments.

#In the budget again

In June 2026 the city council approved the feasibility study for modernising the traffic centre (stage two). On page 62 the study says the FLASH priority module, delivered with the 2019 upgrade, is not in operation "for lack of integration with the fleet-management system at TPBI". TPBI is the association that organises public transport in Bucharest and Ilfov.

The study approved by council decision 243/2026: FLASH, delivered in 2019, is not in operation.
The study approved by council decision 243/2026: FLASH, delivered in 2019, is not in operation. PDF, page 62

On page 214, in its list of required software, the interface for vehicle data ("AVL interface for BUS/TRAM data, SIRI/IRIS type") is described as "could not be identified on the servers of the current BTMS". On the same page the existing priority application is listed as "Flash – Swarco (2019), not operational".

The same study: the vehicle-data interface could not be identified on the current servers; the 2019 priority application is "not operational".
The same study: the vehicle-data interface could not be identified on the current servers; the 2019 priority application is "not operational". PDF, page 214

The study's budget estimate includes 509,243.16 lei excluding VAT for a "BUS/TRAM priority application/module" and 263,608.22 lei for the vehicle-data interface. These are for a system designed for 600 junctions, against about 260 for the current application, according to the same study. They cannot be compared directly with the 2019 price, nor added to it.

Budget estimate from the same study: the vehicle-data interface and a new priority module.
Budget estimate from the same study: the vehicle-data interface and a new priority module. PDF, page 234

The study for the first stage, covering 92 junctions, also requires "putting the priority function into operation", either by completing the current licence or by buying a dedicated one. On 22 June 2026 City Hall announced its application for EU funding and wrote that the new system "will know how to prioritise public transport".

The stage I study (council decision 242/2026): priority must be put into operation.
The stage I study (council decision 242/2026): priority must be put into operation. PDF, page 45

#The bus your phone can see

Bus, tram and trolleybus positions are already public. TPBI publishes a real-time feed used by transit apps. On Sunday 15 November 2026, read every 10 seconds for 31 minutes, it showed 689 vehicles with at least three reports, on the move or at stops. The median gap between two reports from the same vehicle was 14 seconds, and a position typically reached the feed 6 seconds after the vehicle took it. Counted the same way, with at least three reports, a weekday hour (Monday 26 October, 17:00–18:00) had 1,230 vehicles.

The 2026 study, meanwhile, says the interface through which the traffic centre would receive vehicle data could not be identified on its servers, and earlier mentions "difficulties in standardising and aggregating vehicle data in real time".

A public passenger feed is not the same as a priority request. Depending on the method, the traffic-light system may use the vehicle's position, its estimated arrival time and how late it is, and the data must arrive fast enough for the decision at the junction. The feed does show that vehicle positions are collected centrally and passed on automatically. What is missing, according to the study, is the link between the public-transport system and the traffic-light system.

Each dot is an STB, STV or Regio Serv Transport vehicle that reported its position in the public feed on Sunday 15 November 2026, over 31 minutes. Green: buses; yellow: trams; blue: trolleybuses.

#What the traffic-light company is asked to deliver

The Bucharest Municipal Traffic Management Company (CMMTB) maintains and repairs traffic lights under contracts with ASB. In July 2026 the mayor approved a letter of expectations for 2026–2030, published in August with council decision 361: 45 indicators for assessing its management. Two are for monitoring only and one has a weight of zero.

Financial indicators carry 75% of the weight. The eight indicators specific to the company's work, on traffic lights, repairs, investment and operating profitability, carry 4% between them. How much of the traffic-light system works carries 0.5%, as does network modernisation, the share of junctions newly connected to the system. The dividend payout ratio carries 8%.

  • Financial: 75%
  • Corporate governance: 10.5%
  • Employees: 7%
  • Customers: 2%
  • Environment: 1.5%
  • Specific to the job (traffic lights, repairs, investment): 4%
Each square is half a percentage point of the weight of the 45 indicators. Outlines mark dividends (8%), working traffic lights (0.5%) and network modernisation (0.5%).

None of the 45 indicators measures priority requests received and granted to buses or trams, or the time they lose at lights. The letter sets expectations: it does not show what the company achieved or what bonuses its managers received, and it does not explain why the integration is missing.

All 45 indicators
No.Indicator (translated)CategoryWeight2026 target, as written (Romanian)
1Return on equity (ROE)Financial3.0%Minim 1,51%
2Return on assets (ROA)Financial3.0%Minim 2%
3Operating profit marginFinancial5.0%Minim 2,68%
4Net profit marginFinancial5.0%Minim 2,12%
5Net turnover growth rateFinancial5.0%Minim 5%
6Annual net profit growth rateFinancial5.0%Minim 5,03%
7Dividend payout ratioFinancial8.0%Minim 50%
8Capital expenditure ratioFinancial5.0%Minim 2,78%
9Current ratioFinancial5.0%Minim 1
10Quick ratio (acid test)Financial5.0%Minim 1
11LeverageFinancial8.0%>0-<1
12Debt to EBITDAFinancial5.0%Cu 10% mai puțin față de realizările anului precedent dar valoarea să fie întotdeauna >0
13Asset turnoverFinancial5.0%Minim 0,50
14Inventory turnoverFinancial3.0%Minim 1,37
15Receivables turnoverFinancial5.0%Minim 1,77
16Energy consumptionEnvironment0.5%Minim -1,30% față de anul precedent
17Emissions in scope (reduction target set by Romania's Long-Term Strategy)Environment0.5%Minim -5,78% față de anul precedent
18Emissions in scope (reduction target set by the National Energy and Climate Plan)Environment0.5%Minim -0,80% față de anul precedent
19Customer retention rateCustomers1.0%Minim 80%
20Customer satisfaction scoreCustomers0.5%Minim 89%
21Market shareCustomers0.5%Minim 0,07%
22Average training hours per employeeEmployees1.0%Minim 18 ore
23An employee safety system in placeEmployees1.0%DA
24Number of safety trainingsEmployees0.5%Minim 4
25Labour productivityEmployees2.5%Cu 2 puncte procentuale mai mult față de realizările anului precedent
26Number of employees with disabilitiesEmployees1.0%Conform legii
27Pay gap between female and male employeesEmployees1.0%0%
28Share of independent board membersCorporate governance2.0%Minim 80%
29Share of fixed components in the remuneration of executive and non-executive board membersCorporate governance2.0%Minim 100% din valoarea pachetului de remunerare
30Total remuneration packageCorporate governance0.5%Conform legii
31Number of board meetingsCorporate governance1.0%Minim 4
32Board meeting attendance rateCorporate governance2.0%100%
33Share of women on the boardCorporate governance2.0%Minim 40% din totalul administratorilor
34Share of women in senior managementCorporate governance1.0%Minim 33% din totalul cadrelor superioare de conducere
35Risk-management policies in placeCorporate governance0.0%DA
36Full-time-equivalent employeesJobs (monitoring only, no weight)no weightMonitorizare
37New jobs added during the yearJobs (monitoring only, no weight)no weightMonitorizare
38How much of the traffic-light system worksSpecific to the job (traffic lights, repairs, investment)0.5%>90%
39Average time to intervene on a fault (the formula uses repair time)Specific to the job (traffic lights, repairs, investment)0.5%Maxim 4 ore
40Share of planned investment carried outSpecific to the job (traffic lights, repairs, investment)0.5%>70%
41Maintenance cost per signalised junctionSpecific to the job (traffic lights, repairs, investment)0.5%≤ media Europeană
42Network modernisation (newly connected junctions as a share of all BTMS junctions)Specific to the job (traffic lights, repairs, investment)0.5%Conform planului anual aprobat
43Cost variance against the initial estimateSpecific to the job (traffic lights, repairs, investment)0.5%≤15%
44Share of work done in-house rather than subcontractedSpecific to the job (traffic lights, repairs, investment)0.5%>50% din totalul lucrărilor
45Operating profitability (EBITDA)Specific to the job (traffic lights, repairs, investment)0.5%>0

#The money: contracts, estimates and ceilings

The amounts below are of different kinds and must not be added up. A contract price does not show what was paid, a framework ceiling is the most that could be spent over four years, and a study estimate is not yet a contract.

On 14 September 2026 ASB signed framework agreement 87 for servicing, maintaining, repairing and modernising the traffic-light system: a ceiling of 100,894,851.52 lei excluding VAT over 48 months. The award notice in the EU Official Journal shows a single tender, from the group led by SWARCO Traffic Romania with Urban Scope and Altimate. A single tender is not, by itself, evidence of wrongdoing.

DateWhat it isSupplierKind of amountLei, excl. VAT
2019-01-04Contract 02/2019: traffic-centre software upgrade (UTOPIA, OMNIA)SWARCO Traffic Romaniacontract price2,690,724.50
2019-01-04Line 3 of contract 02/2019: public-transport priority licence (included in the amount above)SWARCO Traffic Romanialine within a contract154,985.73
2024-09-02Contract 71/2024: traffic-light servicing and maintenance, to 31 December 2024CMMTBcontract price1,575,783.00
2024-09-02Contract 70/2024: traffic-light repairsCMMTBcontract price2,480,840.47
2025-02-03Framework 2/2025: traffic-light repairsCMMTBframework ceiling8,879,536.22
2026-09-14Framework 87/2026: servicing, maintenance, repairs and modernisation of the system, 48 monthsSWARCO Traffic Romania, Urban Scope, Altimateawarded framework ceiling100,894,851.52
2026-06-04Stage II study: "BUS/TRAM priority application/module"—budget estimate509,243.16
2026-06-04Stage II study: AVL interface for vehicle data (SIRI/IRIS)—budget estimate263,608.22
Award notice TED 639872-2026: the maximum value of the framework agreement.
Award notice TED 639872-2026: the maximum value of the framework agreement. PDF, page 6

#Is your junction in the first stage?

The first-stage study, approved by council decision 242 on 4 June 2026, lists 92 junctions for new traffic-light equipment. On 22 June 2026 City Hall announced its funding application; the public documents read here show no work under way. "Zone" is the project's zone, not the city sector. Two Berzei–Cobălcescu entries (marked *) may cover the same junction.

No.Junction, as written in the studyProject zonePage
1Piata Chirigiu (Tudor Vladimirescu - Calea Rahovei)468
2Alexandriei - Margeanului - Teiusi468
3Calea Rahovei - Alexandriei - Amurgului - Buzoieni - Soldat Croitoru Vasile468
4Calea Rahovei - Barca468
5Calea Rahovei - Petre Ispirescu - Str. Malcoci468
6Calea Rahovei - Progresului469
7Calea Rahovei - Sebastian Mihail - Calea Ferentari469
8Calea Rahovei - Zamfir Olaru - Electromagnetica469
9Piata Rahova (Alexandriei - Intrarea Recas - Fata in fata cu Piata Privata Nicky Scorpion)469
10Sos. Alexandriei - Cora469
11Sos. Alexandriei - Intrarea Ghimes (Posada)469
12Sos. Alexandriei - Sos. Antiaeriana469
13Sos. Alexandriei - Str. Ion Conea469
14Soseaua Alexandriei - Str. Jandarmeriei469
15Gheorghe Marinescu - Cotroceni (Gradina Botanica)569
16Iuliu Maniu - Apusului569
17Iuliu Maniu - Centurii - Dealul Tugulea569
18Iuliu Maniu - Cernisoara569
19Iuliu Maniu - Drumul Bacriului - Vijeliei (Master)569
20Iuliu Maniu - Liceul Tudor Vladimirescu - Str. Politehnicii569
21Iuliu Maniu - Lujerului - Virtutii569
22Iuliu Maniu - Osiei - Metro Militari569
23Iuliu Maniu Practiker (Auchan Militari Shopping)569
24Iuliu Maniu - Rasaritului - Dreptatii570
25Iuliu Maniu - Timonierului - Veteranilor570
26Iuliu Maniu - Valea Cascadelor570
27Iuliu Maniu - Valea Lunga - Floarea Rosie570
28Iuliu Maniu - Vasile Milea570
29Piata Gorjului (Iuliu Maniu - Dezrobirii - Moinesti)570
30Piata Leu (Cotroceni - Geniului - Iuliu Maniu - Grozavesti)570
31Pod Cotroceni (Splaiul Independentei - Constantin Noica)570
32Berzei - Calea Plevnei - Vasile Parvan170
33Berzei - Mircea Vulcanescu - Str. Garii de Nord170
34Berzei - Popa Tatu (Hala MATACHE)170
35Berzei - Stirbei Voda - Cobalcescu *170
36Berzei - Virgiliu - Dinicu Golescu - General H. M. Berthelot171
37Mihail Kogalniceanu - Vasile Parvan - Bogdan Petriceicu Hasdeu171
38Vasile Parvan - Capat Troleibuze - Intrarea Teodor Burada171
39Pod Izvor (Schitu Magureanu - Splaiul Independentei)171
40Calea Mosilor - Ardeleni271
41Calea Mosilor - Dacia - Mihai Eminescu - Str. Traian271
42Calea Mosilor - Fainari - Aleea Cenusaresei271
43Calea Mosilor - Popa Petre - Gen. Grigore Ipatescu271
44Piata Bucur Obor (Stefan cel Mare - Colentina - Mihai Bravu - Calea Mosilor)271
45Trecere pietoni Dimitrie Leonida371
46Trecere pietoni statie Metrou Berceni371
47Trecere pietoni Soseaua Berceni 104 (Toyota)371
48Trecere pietoni Soseaua Berceni 104 (A-G)371
49Berceni - Dossan IMGB371
50Berceni - Metalurgiei - Cheile Turzii371
51Berceni - Turnu Magurele - Iriceanu - Drumul Jilavei (Metrou Aparatorii Patriei)371
52Piata Sudului (Sos. Oltenitei - Calea Vacaresti Berceni - Nitu Vasile)371
53Chitilei - Laminorului - Mezes172
54Chitilei - Neagoe Theodor (Collosseum)172
55Poligrafiei - Tipografilor - Strada Parcului172
56Jiului - Dridu172
57Jiului - Natatiei172
58Piata Presei Libere (Kiseleff - Marasti - Poligrafiei - Bucuresti - Ploiesti)172
59Kiseleff - Aleea Primo Nebiolo (Fost Aleea Strandului)172
60Virtutii - Uverturii572
61Viilor - Ion Baiulescu472
62Viilor - Constantin Istrati472
63Viilor - Fabrica de Chibrituri - Spataru Preda472
64Viilor - Intrarea Viilor (Fabrica de Ciocolata)472
65Viilor - Odoarei - Nasaud472
66Progresului - Nasaud472
67Panduri - Urdareanu572
68Panduri - Doctor Ion Ghiulamila572
69Panduri - Mihai Ciuca - Barbu Urleanu - Capitan Vijelie (Scoala Generala 146)572
70Panduri - Dr. Rainer572
71Panduri - Bagdazar572
72Fundeni - Spitalul Oncologic Fundeni273
73Fundeni - Itcani - Gellu Naum273
74Fundeni - Campul cu Narcise273
75Fundeni - Parcul Motodrom273
76Petricani - Lacul Tei - Doamna Ghica (Palatul GHICA)273
77Lacul Tei - Teiul Doamnei273
78Lacul Tei - Maica Domnului - Grigore Moisil273
79Ferdinand - Mihai Bravu273
80Mihai Bravu - Vatra Lliminoasa - Matei Voievod273
81Nicolae Titulescu - Banu Manta173
82Maltopol - Nicolae Titulescu173
83Nicolae Titulescu - Dr. Felix Iacob173
84Piata Victoriei (Lascar Catargiu - Kiseleff - Aviatorilor - Iancu de Hunedoara - Victoriei)173
85Piata Garii de Nord 1 (Dinicu Golescu - Witing - Intrarea Principala Gara de Nord)173
86Str. Berzei - Str. Cobalcescu *173
87Berceni - Drumul Cretestilor373
88Bd. Iuliu Maniu - acces UNST Politehnica574
89Bd. Iuliu Maniu - TP Automatica574
90Bd. Iuliu Maniu - TP Cora Lujerului574
91Bd. Iuliu Maniu - TP Imprimeria Nationala574
92Bd. Iuliu Maniu - TP Aleea Valea Crisului574

#The records that would show who is responsible

The public documents show a function delivered in 2008–2009, a licence for it contracted in 2019, and a new module in the 2026 budget. They do not show who was meant to connect vehicles to traffic lights, what was tested at acceptance, or whether anything changed after June 2026. That needs the following records, to be requested from the institutions, where they exist:

  1. The acceptance record and technical offer for line 3 of contract 02/2019ASB
  2. The results of the 2019 tram-priority pilot mentioned by the World BankASB, STB
  3. The document assigning responsibility for the interface between the traffic centre and the fleet-tracking systemASB, TPBI, STB
  4. Invoices and payment orders for contract 02/2019ASB
  5. Traffic-centre logs of priority requests received and granted since June 2026the body operating the traffic centre
  6. Specifications and acceptance tests for the new priority module and for framework agreement 87City Hall, ASB

The record also rules some claims out: that priority never worked even in tests (the 2015 report says it passed acceptance tests, and the World Bank mentions pilots in 2008–2009 and 2019), that there was no maintenance (there are maintenance contracts in 2024 and 2025), or that one institution is to blame. No document says so.

How fast Bucharest's buses really move: a day of real positions, 26 October 2026

#Method

Quotations and amounts from official documents were read on the original page. Page numbers are those of the PDF file. Amounts exclude VAT, as in the documents; no amount has been added to another. Quotations are translated from Romanian.

"Never" here means in regular service: the 2026 study says priority "has never worked", the 2015 mobility-plan report that it "was never used operationally", but also that it passed its acceptance tests. The most recent finding in the documents read is in the study approved in June 2026, which does not date its observations exactly.

The feed: TPBI GTFS Realtime, positions read every 10 seconds on Sunday 15 November 2026 for 31 minutes; the weekday count comes from the recording made on 26 October 2026 for the page on real bus speeds, read every 20 seconds.

Earlier reporting: Buletin de București wrote on 13 May 2026 about the new investment and the system that had not worked for over a decade; B365 wrote on 6 October 2026 about the expansion announced by City Hall.