Lit points: substations and plants named in the report. Black-start plants are anonymised and shown by area. City lights dim and return together, with national consumption: the report does not say when each city came back.
Spain and Portugal · 28 April 2025
The great Iberian blackout: 27 seconds to go dark, 16 hours to come back
At 12:33 on a sunny Monday, continental Spain and Portugal lost all their electricity. The investigators' final report and Red Eléctrica's five-minute data let the day be replayed, first in milliseconds, then in hours.
Scroll: the clock runs with you
09:00 – 12:32
A normal Monday, full of sun
At half past twelve mainland Spain was using 25,184 MW. Solar plants were producing 19,156 MW, about three quarters of that, and Spain was exporting 4,311 MW, almost all of it to Portugal, France and Morocco.
From about nine, voltages on the 400 kV grid had been wandering more than usual. Twice in the last half hour the system oscillated: from 12:03 to 12:08 at 0.63 hertz, a forced oscillation driven by power electronics, strongest between Carmona and Almaraz in the south-west, next to an inverter-based plant, and from 12:19 to 12:22 at 0.2 hertz, a swing across the whole continent.
Both swings died down. Operators cut exports to France, coupled lines in the south and changed the mode of the direct-current link to France. The report finds these measures clearly effective against the second swing and of minor help against the first, and notes that they also pushed voltage up. At 12:32:00 the 400 kV grid was below 420 kV and calm.
12:32:57.220
The first trip, in Granada
A 400/220 kV transformer in the Granada area, which collects the output of several solar, wind and solar-thermal plants, is disconnected by its overvoltage protection. It was injecting 355 MW. The voltage on the 400 kV side was 417.9 kV, inside the normal range.
Its owner said the relay was set to trip at 242 kV on the 220 kV side, with no delay. The report lists the trip as diverging from the rules, notes that 523 MW of the plants behind the transformer belong to an older category outside those rules, and could not establish why the relay saw a voltage above its setting: a measurement transient or a relay error is possible.
A plant that drops out also stops absorbing reactive power, the part of the current that was holding voltage down. So the trips lift the voltage for the plants still connected.
12:33:16.443 – 12:33:18.951
Eighteen more in two and a half seconds
Nineteen seconds later the chain begins. Badajoz: 582 MW, then 145 MW. Segovia, Sevilla, Cáceres, Huelva, Cádiz, Murcia, Málaga. By 12:33:18.951, when 530 MW of solar plants at a substation in Cuenca drop out, 2,990 MW of generation has been lost in 19 trips.
The chart below the map shows the voltage each plant saw when it tripped, rising from 417.9 to 448.6 kV. For 9 of the 19, carrying 1,867 MW, the report says the protection settings diverged from the requirements. Three were consistent with the rules and three possibly so; for three the records were missing, and one plant had no requirement to meet.
Until 12:33:18 no plant tripped in Portugal or France.
12:33:19 – 12:33:21.535
The frequency falls, and the neighbours cut the cable
With gigawatts of generation gone, the turbines still turning slow down and the frequency drops below 50 hertz. At 12:33:19 Spain and Portugal begin to lose step with the rest of Europe.
The defence plans fire as designed. Pumped-storage plants stop pumping and whole districts are shed in steps from 49.0 hertz downwards. They cannot stop the collapse: the report says this was because it was driven by overvoltage.
At 12:33:20.473 the last cable to Morocco opens. At 12:33:21.407 the line from Baixas, in France, to Vic in Catalonia trips; at 12:33:21.535 the line to Hernani follows. Their protections cut Iberia loose so the disturbance would not spread across Europe. Apart from a small area of south-west France, briefly affected, the rest of the continent felt nothing.
12:33:22 – 12:33:26
Dark
The nuclear units that were running, 3,390 MW between them, trip between 12:33:22.702 and 12:33:23.590. At 12:33:23.960 the direct-current link to France, still exporting, is blocked. The lines between Spain and Portugal open between 12:33:25 and 12:33:26.
Mainland Spain goes from 25,184 MW to zero; Portugal too. What stays lit are the islands: the Balearics, cut from the peninsula at 12:33:23.520, kept their own power, as did the Canaries, Ceuta and Melilla. Together they were using 1,778 MW.
From the first trip to the blocking of the link to France, which completed Iberia's separation from Europe: 27 seconds. ENTSO-E calls it the worst blackout in Europe in more than 20 years, and the first ever caused by overvoltage.
12:33 – 13:35
Three doors back in
At 12:36 Red Eléctrica asks France's grid operator for voltage through the Hernani and Vic lines. At 12:43 the 400 kV line from Argia, in France, energises Hernani, near San Sebastián. It is the first substation on the peninsula with power again, and the start of the Northern zone.
At 13:04 Morocco, which had agreed to send up to 100 MW, energises Tarifa through a submarine cable: the Southern zone begins, at Moroccan frequency. At 14:27 the cable trips when Morocco's own frequency dips, and the link is restored at 14:34.
At 13:35 the line from Baixas switches on at Vic: the Eastern zone, Catalonia's, begins.
12:55 – 16:06
A dozen dams try to start on their own
Each restoration area has hydro plants that can start without outside power. From 12:55 they are switched on one by one to build small islands of grid: in Extremadura, on the Duero, in Asturias, Galicia, Cantabria, Levante and Aragón.
Many fail. The Extremadura island collapses at 13:56. The first Duero plant trips at 13:12, East Asturias at 13:23. In Andalucía and Madrid no island forms at all. Levante goes at 16:03 and Cantabria at 16:06. The report lists the faults: units that could not regulate frequency, protections set to trip at 49.5 hertz against the rules, telephones that did not work.
At 15:07 every nuclear plant again has outside power for its cooling and auxiliary systems. Where an island failed, the area was re-energised from a neighbouring zone when possible.
13:35 – 19:53
Catalonia: the door that lit the east
Vic was the first link to France to break, at 12:33:21.407. At 13:35 it was the door through which the east came back. The voltage from Baixas was used to power the auxiliary services of thermal plants and critical loads, and became the Eastern zone.
At 15:59 one link of the direct-current cable between Baixas and Santa Llogaia, in the Empordà, was switched on. At 16:34 the Eastern zone sent stable power south along the La Plana–Masdenverge line to restart the thermal plants of northern Levante. At 17:23 it energised the La Muela substation, in the Levante area, and the hydro plants there were connected to it.
At 16:54 the Northern zone reached the Aragón island. At 19:53 the Peñaflor–Aragón line joined north and east, and mainland Spain had a single restoration area.
16:20 – 19:53
The pieces are stitched together
From late afternoon the islands and zones are synchronised one by one. Duero joins the north at 17:49; the south and the Extremadura island are linked at 18:16. At 18:36 Spain sends voltage into Portugal through Aldeadávila–Pocinho, the first time Portugal receives continental frequency again.
At 19:32 the north, from the Basque Country to Galicia, is synchronised with the south, from Andalucía to Madrid. Load supplied: 8,827 MW, about a third of what is normal at that hour.
19:53 – 04:00
The night of reconnection
The curve climbs. At 22:15 use reaches half of what is normal at that hour. By midnight mainland Spain is drawing 15,300 MW.
Portugal's transmission grid is fully restored at 00:22. Spain's follows around 04:00: by then, says Red Eléctrica, every substation of the transmission grid had power.
Tuesday 29 April
Back on is not back to normal
Red Eléctrica said that by 7:00 on Tuesday 99.95% of demand had been restored. It did not say how it measured that; since use at that hour was well below normal, it most likely means that almost all supply points could draw power again. How much they actually drew is another matter. At 7:00 mainland Spain drew 20,816 MW, 83% of a normal Tuesday at that hour. Between 3 and 6 in the morning it was 72%.
Over the whole Tuesday, use was 84% of a normal Tuesday. On Wednesday it was back to 96%. The yardstick holds: on Monday morning, before 12:33, the same measure stood at 101%.
Why it happened, according to the investigators
On 20 March 2026 an expert panel of 49 members, from transmission operators and energy regulators across Europe (Romania's among them), published its final report. It found no single cause. Several factors combined, and the panel says solutions were already technically feasible.
Low margin. Spain's rules let its 400 kV grid reach 435 kV, above a normal range of 390–420 kV; Portugal's limit is 420 kV. That left little room between the highest voltage the grid could run at and the voltage at which plants were allowed to disconnect.
Renewables were not asked to control voltage. Under the Spanish rules in force that day, wind and solar plants ran at a fixed power factor: the reactive power they absorb follows their output, not the voltage. They were technically capable of more, but the rules did not require it, so they did not react when voltage rose.
Conventional plants helped less than required. Some diverged from the reactive-power requirements; the rules carried no specification for fast behaviour and no penalty.
Voltage-control equipment was switched by hand. At 12:32 about 58% of the capacity of Spain's shunt reactors was connected; the rest could not be connected in time.
Protections tripped too early. Many protection settings diverged from the requirements or did not match the system's needs, and small rooftop units under 1 MW dropped out unseen by the grid operator.
The report does not assign blame; that falls to national authorities. Some data never arrived: for many of the early trips, no records from the protection that operated were delivered to the panel.
The 19 generation disconnections in Spain before 12:33:19
Source: ENTSO-E final report, Table 3-3. Voltage measured or estimated at the moment of the trip; 220 kV rows are on a 220 kV scale. Verdict as given by the report.
Time
Province
Grid
Technology
MW
Voltage at trip
Report's verdict
12:32:57.220
Granada
400 kV
solar PV, wind, solar thermal
355
417.9 kV
diverges
12:33:16.443
Badajoz
400 kV
solar PV, solar thermal
582
432.6 – 437.3 kV
diverges
12:33:16.820
Badajoz
400 kV
solar PV
145
438.7 kV
diverges
12:33:17.368
Segovia
400 kV
wind
22.9
436.5 kV
aligns
12:33:17.520
Badajoz
400 kV
solar PV
118
443 kV
possibly aligns
12:33:17.547
Huelva
220 kV
wind, solar PV
33.7
–
unknown
12:33:17.780
Sevilla
400 kV
solar PV
550
437.7 kV
diverges
12:33:17.940
Segovia
400 kV
wind
94
443.4 kV
aligns
12:33:17.975
Cáceres
220 kV
solar PV
37.5
250.4 kV
diverges
12:33:18.020
Badajoz
220 kV
solar PV
71.9
–
unknown
12:33:18.102
Sevilla
220 kV
solar PV
3
246.5 kV
diverges
12:33:18.220
Badajoz
220 kV
solar PV
20
–
unknown
12:33:18.360
Badajoz
400 kV
solar PV
16
447.7 kV
aligns
12:33:18.410
Cáceres
400 kV
solar PV
41
444.3 kV
diverges
12:33:18.540
Murcia
400 kV
solar PV
63
–
no requirement applied
12:33:18.630
Cádiz
220 kV
solar PV
25.7
247.5 kV
diverges
12:33:18.680
Cádiz
220 kV
solar PV
127.5
248.2 kV
diverges
12:33:18.846
Málaga
400 kV
solar PV
154
448.6 kV
possibly aligns
12:33:18.951
Cuenca
400 kV
solar PV
530
448.6 kV
possibly aligns
Two days of electricity use, every five minutes
Mainland Spain, Monday 28 and Tuesday 29 April 2025, against the average of the same weekdays one and two weeks later (5–6 and 12–13 May). Point at the chart to read a time.
Questions people ask
How long did the blackout in Spain last?
The grid collapsed at 12:33 on 28 April 2025. Portugal's transmission grid was fully restored at 00:22 on 29 April and Spain's around 04:00; the investigators count about 16 hours for Spain and 12 for Portugal. Many homes had power back well before that, others only in the small hours.
What caused the blackout?
A rapid, uncontrolled rise in voltage in southern Spain, which made plant after plant disconnect until the system collapsed. The ENTSO-E panel names several combined factors: little margin between normal and tripping voltage, renewables that, under the rules in force, were not required to regulate voltage, conventional plants that did less than required, hand-switched reactors and protections set too low. All the causes it lists are technical: voltage control, protection settings and the way the grid was run.
Was Catalonia affected?
Yes, all of mainland Spain went dark, Catalonia included. Catalonia was also one of the three doors back in: at 13:35 the line from Baixas, in France, energised Vic. From there the Eastern zone grew south into the Valencian region, and at 19:53 the Peñaflor–Aragón line joined it to the Northern zone.
Did the Balearic and Canary Islands lose power?
No. Their grids are separate or were cut off: the cable between the peninsula and Mallorca was blocked at 12:33:23.520 and the Balearics kept their own supply. The Canaries, Ceuta and Melilla were unaffected.
Times are Central European Summer Time (Spain's clock; Portugal is an hour behind). Electricity use is Red Eléctrica's peninsular demand, every five minutes. The normal day is the average of the same five-minute slot one and two weeks later. Positions of black-start plants are approximate: the report gives only their area. On the map, city lights dim and return together with national consumption; the report does not say when each city got power back.
ENTSO-E Expert Panel, Final Report on the Grid Incident in Spain and Portugal on 28 April 2025, 20 March 2026 (sequence of events: Table 3-1; generation trips: Table 3-3; restoration: Chapter 5). eepublicdownloads.blob.core.windows.net
ENTSO-E, 28 April 2025 Blackout: reports, letters and the media briefing of the final report. www.entsoe.eu
Red Eléctrica, peninsular electricity demand and generation, every five minutes (REE demand viewer). demanda.ree.es
Red Eléctrica, Red Eléctrica’s response to the incident of 28 April (restoration figures, 99.95% at 07:00). www.ree.es
Natural Earth (provinces, populated places); NOAA ETOPO 2022 (relief); OpenStreetMap Nominatim (places named in the report). www.naturalearthdata.com