The Bucharest–Danube Canal, 1986–2026

Bucharest was meant to be a Danube port

Work began in 1986 on a planned 73-kilometre waterway linking Romania’s capital to the Danube along the Argeș River. In early 1990 it stopped. The locks were left standing in the fields.

A canal along the Argeș valley

Decree 242 of 4 July 1986 approved the route of the works on the Argeș, and Decree 292 of 28 December 1987 covered the lower Dâmbovița. Besides shipping, the canal was meant to irrigate the plain and protect villages from the Argeș floods.

The Argeș waterway was to run 73 kilometres and reach the Danube near Oltenița. A second branch, on the Dâmbovița, was to lead to Glina.

Fifty-three metres, in four steps

According to the documentation cited in 2024 by Economedia, the design allowed for a 53-metre descent between Bucharest’s port and the Danube. Ships would have passed four sets of twin locks, at Copăceni, Goștinari, Budești and Oltenița.

On the Argeș, the design called for a navigable depth of at least 4.5 metres and a bottom width of at least 80 metres. For the whole waterway, estimated capacity was 24 million tonnes of freight a year.

The port near 1 Decembrie

The basin of Bucharest’s port was dug near the commune of 1 Decembrie, south of the capital; it still shows on the map. A second port for Bucharest was planned at Glina, on the Dâmbovița.

According to the canal authority, over 80% of the infrastructure of the port platforms at Oltenița and Bucharest was done before work stopped; at Glina the quays and about 30% of the platforms had been built.

Twenty-five thousand people

The canal’s National Youth Worksite opened with a ceremony on 5 August 1986. According to Jurnalul Național, 25,000 people worked on the site.

Earthworks and embankments were about 70% done and bank protection about 40%, according to the national forecasting commission study cited by Adevărul in 2018.

Opening of the National Youth Worksite “Danube–Bucharest Canal”, 5 August 1986.
Opening of the National Youth Worksite “Danube–Bucharest Canal”, 5 August 1986. Photographer unknown. © National Museum of Romanian History, via Wikimedia Commons.

Early 1990: everything stops

According to the project documentation, work was suspended in January 1990 after funding stopped; Jurnalul Național puts the halt in February. The same report estimated the project 60% complete, while Digi24 gave 70%.

The locks were left unfinished in the middle of the fields. The Mihăilești–Cornetu dam and reservoir, upstream of the port on the lower Argeș, are in operation.

The unfinished Copăceni lock, 20 May 2007.
The unfinished Copăceni lock, 20 May 2007. Photo: VictorPlastic, Wikimedia Commons, CC BY 3.0.

What finishing it was estimated to cost

In 2008 the transport minister put the remaining 30% of the works at about 450 million euros. The 2012 feasibility study reached 1.38 billion euros excluding VAT, and the 2018 study 1.44 billion excluding VAT.

The 2024 version of the study estimated 22.1 billion lei including VAT and 70 months of work.

Feasibility study delayed to the end of 2026

On 4 December 2025 a flood on the Argeș broke the makeshift bridge between Budești and Crivăț. In January 2026 the canal authority said the revised feasibility study could be finished at the end of the year, if water and environmental approvals came through.

At that point it could not say when construction would resume.

Sail down to the Danube

Drag the bar to sail down from Bucharest’s port to the Danube. The map follows the Argeș in OpenStreetMap for 75.6 kilometres; the designed route was about 73.

The canal’s profile, schematic

0204060CopăceniGoștinariBudeștiOltenița
Schematic profile based on terrain elevations near the port and the locks; it does not reproduce the design levels.

Estimates for completing the canal

million euros

  • 2008450minister’s estimate for the remaining 30% (VAT basis not given)
  • 20121,380feasibility study, excl. VAT, 2012 prices
  • 20181,440national forecasting commission study, excl. VAT
  • 20242024 version of the study: 18.6 billion lei excl. VAT (22.1 incl. VAT)

How the map is made

The Copernicus GLO-30 elevation data were resampled to a grid of about 90 metres and filtered to reduce the influence of buildings and vegetation; height is exaggerated 14 times so the valley shows. Villages and woods come from ESA WorldCover 2021, water from WorldCover and JRC Global Surface Water.

The canal route follows the Argeș in OpenStreetMap for 75.6 kilometres, from near the Port București basin to the Danube; the designed route was about 73 kilometres. The locks and the port basin are placed where OpenStreetMap has them. The branch to Glina follows the Dâmbovița.

The water level of each reach is schematic: the first reach sits at the terrain height near the port, the next ones at the terrain height near the upstream lock. The difference comes to about 48 metres, close to the 53 in the 2024 documentation. The canal’s width is exaggerated so it can be seen.

Send the map

For anyone driving past Budești or Copăceni who sees the locks in the fields.

More on the Danube

Sources

The documents, articles and data used for the text and the map.

  1. Economedia, „Canalul București–Dunăre: costul total estimat este de 22 miliarde lei…”, iunie 2024 (date CNACN: 73 km, patru noduri hidrotehnice, 53 m, 4,5 m adâncime). economedia.ro
  2. Economedia, „Canalul Dunăre–București, amânat din nou”, 15 ianuarie 2026. economedia.ro
  3. Gândul, „Canalul Dunăre–București. Stadiul unuia dintre proiectele majore…”, 18 noiembrie 2024 (decretele 242/1986 și 292/1987, porturile, oprirea din ianuarie 1990). www.gandul.ro
  4. Adevărul, „Guvernul reia proiectul Canalului Dunăre–București”, 17 decembrie 2018. adevarul.ro
  5. Digi24, „Canalul Dunăre–București scos de la naftalină”, 17 decembrie 2018. www.digi24.ro
  6. Jurnalul Național, „Canalul broaștelor”, 22 iulie 2005. jurnalul.ro
  7. Comisia Națională de Strategie și Prognoză, studiu de fundamentare pentru amenajarea Argeș–Dâmbovița (decretele 242/1986 și 292/1987). cnp.ro
  8. Europa Liberă România, viitura de pe Argeș, 4 decembrie 2025. romania.europalibera.org
  9. Copernicus GLO-30 (relief), ESA WorldCover 2021 (CC BY 4.0), JRC Global Surface Water, OpenStreetMap (ecluzele Copăceni, Goștinari, Budești, Oltenița și Portul București; © OpenStreetMap contributors, ODbL). www.openstreetmap.org