The cold in the contract

Bucharest’s district heating, judged by softer rules: limits raised in 2025, guarantees relaxed in 2026

In 2024 the city heating company’s network lost more heat than its contract allowed. In November 2025 the limits were raised above the results. In April 2026 the guarantee that counted, for each supply contract, the hours of hot water or heating below standard was given a “total waiver”, then extended back over 2025.

Your building’s heat substation ↓Am I owed compensation? ↓

The same 2024 results, two sets of limits
  1. Heat loss, transmission network

    over the limitwithin the limit Heat loss, transmission network: 29.15%; limit 23%; over the limit.

  2. Heat loss, distribution network

    over the limitwithin the limit Heat loss, distribution network: 12.64%; limit 11.5%; over the limit.

  3. Top-up water, transmission network

    over the limitwithin the limit Top-up water, transmission network: 6.20 m³/Gcal; limit 3.5 m³/Gcal; over the limit.

  4. Top-up water, distribution network

    over the limitwithin the limit Top-up water, distribution network: 1.11 m³/Gcal; limit 0.5 m³/Gcal; over the limit.

4 of 4 results over the limit0 of 4 results over the limit

The same results reported for 2024, measured against two sets of limits. The comparison does not show that the new rules were applied retroactively or that any penalty was cancelled.

Sources: ADITBI Decision 16/2025, art. 1; ADITBI monitoring report for 2024, pages 12 and 15. H16 · 2024 report

#Four results over the limit, four limits moved above them

Bucharest’s district heating is entrusted to a company owned by City Hall, Compania Municipală Termoenergetica București (CMTEB), under delegation contract no. 7 of 29 November 2019. The other party to the contract is the association of local councils that oversees the service, ADITBI (the Bucharest-Ilfov intercommunal heating association). Annex 8 of that contract sets, among other things, how much heat the network may lose on the way.

The transmission network carries hot water from the power plants to the heat substations in each neighbourhood (in Romanian, “puncte termice”). The distribution network takes it on from each substation to the blocks of flats. In ADITBI’s report for 2024, the transmission network lost 29.15% of the heat that entered it. The contractual limit was 23%.

On 4 November 2025 ADITBI’s general assembly adopted Decision 16, changing four of those limits. All four results reported for 2024 were over the old limits. All four fall within the new ones. The limit for top-up water in the distribution network went up seven times.

The four limits changed by ADITBI Decision 16/2025 and the results in ADITBI’s report for 2024
MeasureOld limit2024 resultNew limitNew/old
Heat loss, transmission network23%29.15%33%×1.43
Heat loss, distribution network11.5%12.64%14%×1.22
Top-up water, transmission network (m³/Gcal)3.56.207.0×2.00
Top-up water, distribution network (m³/Gcal)0.51.113.5×7.00

Top-up water (“apă de adaos”) is water added to the circuit to replace what leaks out, per unit of heat delivered. Transmission and distribution losses have different bases and cannot be added. The decision also prints conversions to m³/MWh that do not match the m³/Gcal values arithmetically; the table keeps the Gcal units used in the contract.

The decision lists its grounds: a CMTEB letter of 4 July 2023, a heat balance of the transmission and distribution networks for 2022 drawn up by a consultancy, and an ADITBI background note of 25 September 2025. Neither the balance nor the note is published with the decision.

In summer, more than half of the heat is lost in the transmission network

CMTEB’s report for 2025 gives the loss month by month. From May to September, when the heat it carries is used only to prepare hot tap water, it goes above 60%. The annual figure rose from 29.16% in 2024 to 30.53% in 2025: above the old limit, below the new one.

Monthly heat loss in the transmission network, CMTEB, 2024, 2025 and the first half of 2026
202420252026, Jan–Jun
0%20%40%60%80%Limits in the contract: 23%New limits: 33%January 2024: 25.49%January 2025: 30.68%January 2026: 27.14%JanFebruary 2024: 10.79%February 2025: 21.25%February 2026: 19.99%FebMarch 2024: 30.04%March 2025: 33.04%March 2026: 25.13%MarApril 2024: 55.69%April 2025: 34.48%April 2026: 30.82%AprMay 2024: 63.67%May 2025: 63.37%May 2026: 62.46%MayJune 2024: 69.66%June 2025: 64.74%June 2026: 60.57%JunJuly 2024: 70.74%July 2025: 63.16%JulAugust 2024: 68.78%August 2025: 70.50%AugSeptember 2024: 61.19%September 2025: 65.37%SepOctober 2024: 18.98%October 2025: 39.72%OctNovember 2024: 20.80%November 2025: 12.02%NovDecember 2024: 14.44%December 2025: 10.28%Dec

The limits are annual; the lines show where each month falls against them. Source: CMTEB report for 2025, page 45, and report at 30 June 2026, page 57.

The values, as a table
Month202420252026
January25.49%30.68%27.14%
February10.79%21.25%19.99%
March30.04%33.04%25.13%
April55.69%34.48%30.82%
May63.67%63.37%62.46%
June69.66%64.74%60.57%
July70.74%63.16%–
August68.78%70.50%–
September61.19%65.37%–
October18.98%39.72%–
November20.80%12.02%–
December14.44%10.28%–
year29.16%30.53%29.20% (Jan–Jun)

The comparison does not show that Decision 16 wiped out penalties for 2024. ADITBI’s report says missed indicators lead to penalties set in Annex 8, and that it comes with an annex giving “the amount of the penalty for each indicator not met”. The published file stops at page 41 of 45 and the annex is not in it. Which penalties were calculated, and whether they were paid, does not appear in the public documents consulted.

#The guarantees for residents: what was relaxed in April 2026

The limits above concern the network, between City Hall and its company. For people in the blocks a different set of rules matters: the performance standard of ANRE, the national energy regulator, published in the Official Gazette on 2 October 2024. For each supply contract it sets how many interruptions, and how many hours of hot water or heating below standard, may pass in a year before the operator owes compensation, calculated as a share of the bill.

The standard lets a local authority approve wider, temporary levels while the network is being modernised. On 16 April 2026 ADITBI did so for the heating company, in Decision 14:

Unplanned interruptions

National standard4interruptions per year and contract12days per year and contract
Bucharest heating company, from April 202625interruptions per year and contract75days per year and contract

A year has 365 days. The national threshold: 12 days of interruption. The local one: 75.

In the standard an interruption means hot water or heating has stopped flowing for more than 24 hours. Compensation, 0.7% of the bill for a month of similar consumption in the previous year for each day over the threshold, is due only when both the number and the total duration are exceeded.

Overruns on announced works

National standard250hours per year and contract
Bucharest heating company, from April 2026300hours per year and contract

Only the hours beyond the announced length of the works count, not the whole outage. Compensation: 0.03% of the bill for a month of similar consumption in the previous year, for each extra hour.

Hours of hot water or heating below standard

National standard250hours per year and contract
Bucharest heating company, from April 2026total waiverno threshold

Hours when hot water or heating reach the building outside the contractual limits: too cold, or at too low a pressure. The standard’s compensation: 0.03% of the bill for a month of similar consumption in the previous year, for each hour over the threshold.

Faulty meter

National standard10working days
Bucharest heating company, from April 202620working days

How many working days the operator has to resolve a justified complaint about a meter. Compensation: 30 lei for each day of delay.

The comparison is with the national default. The standard allows a local transition; how far the waiver reaches and what it does to payments needs to be clarified.

Three dates to keep apart

  1. 16 April 2026Decision 14 approves the transitional levels for the period “2026–2029”. PDF
  2. 28 April 2026Decision 24 calls that period a clerical error: the correct period is 2025–2029, and Decision 14 is to “take effect” in that form. On paper the relaxed levels therefore also cover 2025, a year already over; what that means for compensation relating to 2025 does not appear in the documents consulted. PDF
  3. 31 December 2027Decision 15 gives the company until then to finalise and send ADITBI the internal procedures required by the standard, including those for paying compensation and for recording interruptions and departures from standard. The standard separately required the procedures to be drawn up and published within six months; what the local deadline does to that obligation does not appear in the documents. PDF

#Am I entitled to compensation if I have no hot water?

Under the national standard, yes, in some cases, and without asking. For interruptions and for hours below standard, the operator must review every contract in the first quarter of each year for the previous year and pay what is due “without the affected users having to send requests” (articles 27, 32 and 40). Automatic payment depends on an IT system, which the standard required within nine months of coming into force (article 53).

For the Bucharest heating company the rules changed after the first quarter of 2026, that is after the window in which 2025 should have been reviewed. The transitional levels were approved on 16 April and extended over 2025 on 28 April.

For hours of hot water or heating below standard, Decision 14 sets no level at all, only a “total waiver”. The standard says that during a transition compensation is paid “when the transitional guaranteed levels are exceeded” (article 55, paragraph 4). The decision contains no level that could be exceeded. Whether a waiver with no threshold falls within the power the standard grants is not settled by any of the documents consulted; none of them contains an ANRE position or a court ruling on the question.

For interruptions, a building’s contract would need more than 25 interruptions of over 24 hours in a year, and more than 75 days in total. In blocks of flats the supply contract usually belongs to the owners’ association, at the level of the building’s connection; a single flat has no threshold of its own. The standard rules out compensation, among other cases, for force majeure, for frosts below the design temperature in the contract, or when the building’s own installations are faulty (article 4).

There is also an older mechanism in the service regulations: a reduced bill when the contractual parameters are not met. For 2024 ADITBI reports 86 requests, 27 of them approved, and another 195 cases in which the distribution sections applied the reduction, with 513.37 MWh taken off bills. In March 2026 the City Council asked ADITBI to check how this compensation under the regulations is granted, a mechanism separate from compensation under the ANRE standard.

Documents that help an owners’ association

  • the supply contract and the annex naming the delivery point (the building’s connection)
  • the service affected: hot water, heating or both
  • the association’s own log of outages and temperatures, with dates and times
  • meter readings at the connection for the periods in question
  • complaints registered with CMTEB, with number and date
  • the bill for a month of similar consumption in the previous year, the basis for compensation
  • the reply or payment received

The public notices on the map concern a heat substation, not a particular building. On their own they do not prove compensation is owed; they show where the documents above are worth asking for.

#How many hours of below-standard hot water notices your heat substation had in 2025

CMTEB publishes the state of its network online: which heat substation has a problem, with which service and why. An independent project, termoficare-data, saved that page every hour. The archive for January 2025 to October 2026 holds 991,117 records from 10,528 captures.

From it, the hours have been reconstructed in which a substation showed a notice of hot water delivered below standard (“lipsă parametri”, “funcționare deficitară”) in two consecutive captures no more than three hours apart. It is the closest public signal to the indicator that was waived. In 2025, 141 substations passed 250 hours, the national threshold per year and contract.

141substations with more than 250 hours in 2025
1,691hours at 1 Cheile Zănoagei, the most in the city
69.9%of 2025’s hours covered by usable captures

Pick a heat substation on the map or in the search.

Hours with a below-standard hot water notice, 2025under 100100–250250–500over 500no data

The 2025 and 2026 figures are not directly comparable: 2026 is incomplete, and usable captures cover 54.8% of its hours against 69.9% in 2025.

Heat substations with the most hours in 2025

#Around Lake Tei: five heat substations with more than a thousand hours each

14 of the top 15 heat substations in 2025 are in the north-east of the city, between Lake Tei, Colentina and Doamna Ghica. At 1 Cheile Zănoagei, the substation for the T blocks on Petre Antonescu, Grigore Ionescu, Brebu, Oteșani and Cristea Mateescu streets, below-standard hot water notices add up to 1,691 hours, captured on 156 calendar dates. Next to it, 3 Cheile Zănoagei: 1,575 hours on 154 dates.

Most notices give the same cause, “parameters for delivering hot tap water not met”; some tie it to modernisation works on the mains leaving the CTE Sud plant or to failures on the primary network. The number of dates does not mean whole days without hot water.

In 2026, up to the last usable capture on 23 October, the largest total is at 1 Labirint, on Matei Basarab street: 986.3 hours with notices, captured on 107 calendar dates.

1 Cheile Zanoagei, 2025: 1,691 hours
0100200300400January 2025: 98 hoursJanFebruary 2025: 3 hoursFebMarch 2025: 102 hoursMarApril 2025: 211 hoursAprMay 2025: 130 hoursMayJune 2025: 300 hoursJunJulAugust 2025: 109 hoursAugSeptember 2025: 209 hoursSepOctober 2025: 302 hoursOctNovember 2025: 212 hoursNovDecember 2025: 15 hoursDec
3 Cheile Zanoagei, 2025: 1,575 hours
0100200300400January 2025: 95 hoursJanFebruary 2025: 98 hoursFebMarch 2025: 143 hoursMarApril 2025: 185 hoursAprMay 2025: 93 hoursMayJune 2025: 212 hoursJunJulAugust 2025: 143 hoursAugSeptember 2025: 220 hoursSepOctober 2025: 155 hoursOctNovember 2025: 227 hoursNovDecember 2025: 4 hoursDec
1 Labirint, 2026: 986 hours
0100200300400January 2026: 202 hoursJanFebruary 2026: 50 hoursFebMarch 2026: 170 hoursMarApril 2026: 133 hoursAprMay 2026: 237 hoursMayJune 2026: 104 hoursJunJulAugust 2026: 62 hoursAugSeptember 2026: 26 hoursSepOctober 2026: 2 hoursOctNovDec

A month with no bar is not necessarily zero: some intervals were not captured.

#How it came to this

  1. ANRE

    In the consultation on the new standard, CMTEB proposes guaranteed levels adapted to each system’s condition. ANRE refuses: performance must be comparable, and a single threshold is an incentive to invest. source

  2. ANRE

    CMTEB and ADITBI ask for local flexibility while investments are under way. Other operators ask for adjustments too. ANRE’s reply introduces the transition mechanism. source

  3. CMTEB

    CMTEB letter no. 56647, which Decision 16 will cite in 2025 among its grounds for raising the limits. source

  4. ANRE

    CMTEB asks to drop, for now, the duty to record interruptions and departures from standard: it has neither software nor staff, and a system would cost “over 100 million euros”, by the company’s estimate. ANRE refuses: the records are compulsory however they are kept, by hand if need be. source

  5. ANRE

    The performance standard appears in the Official Gazette. Deadlines: six months for internal procedures, nine months for the IT system behind automatic payments. source

  6. CMTEB · ADITBI

    A CMTEB–ADITBI meeting, recorded in minutes no. 75606, which Decision 14 cites. The document is not published with the decision. source

  7. ADITBI

    Decision 16 raises four network performance limits. source

  8. City Council

    Decision 64 instructs ADITBI to check the procedure for compensating users whose supply did not meet the agreed parameters or continuity. source

  9. Standard

    The first quarter ends: the window in which the standard requires every contract to be reviewed for the previous year. source

  10. ADITBI

    Decision 14 approves the transitional guarantees, with a total waiver for hours below standard. Decision 15 gives the procedures until 31 December 2027. source

  11. ADITBI

    Decision 24 corrects the period to 2025–2029. source

  12. Deadline

    Deadline for finalising the procedures, including the one for paying compensation. source

  13. Deadline

    End of the approved transition period. source

#The arguments on the other side

The standard allows a transition. Article 55 lets a local authority with projects to modernise, rehabilitate or extend the network, under way or planned in the local heating strategy, set a transition period and transitional levels; the period may not run past the completion date in the strategy, and the levels take the state of the installations into account. Bucharest has such a programme, with works on 212 km of pipe, mapped in “Why your hot water is off”. The grounds listed in Decision 14 are the standard, the contract, the service regulations, the June 2025 minutes and a background note; it does not cite article 55, nor the investment projects that article refers to. The standard also says transitional levels “may be set annually”, according to the investments completed the year before.

The network is not getting uniformly worse. In the first half of 2026 transmission losses fell to 29.20% from 33.27% in the same period of 2025. In distribution they rose from 10.29% to 11.69%.

Compensation cannot be passed on in prices. The standard bars including it in tariffs or in losses covered from the local budget (article 51). The company pays it, and can recover it from City Hall or ADITBI only if it proves the faults come from tariffs or investments those bodies failed to approve or carry out (article 4).

The sources do not give the same values for 2024. ADITBI’s report has 29.15% transmission loss and 12.64% distribution loss; CMTEB’s report for 2025 gives 29.16% and 12.58% for the same year. The differences are small and do not change the position against the limits.

#What the public documents do not say

  1. How the four new limits were justified: the 2022 heat balance and the September 2025 note are not published with the decision.
  2. What penalties were calculated for 2024 and whether they were paid: the penalty annex is missing from the published report.
  3. Which projects and deadlines justify each transitional threshold and the total waiver.
  4. Whether the levels were notified to ANRE, as article 56 requires, and what the regulator replied.
  5. What the company reviewed for each contract in the first quarter of 2026, and what compensation it calculated for 2025, before and after the correction of 28 April.
  6. How interruptions and departures from standard are being recorded now, records ANRE declared compulsory back in 2023.

#How the hours were calculated

The source is the public termoficare-data archive, the version fixed at commit 76db291, with CMTEB status pages captured between 1 January 2025 and 23 October 2026. A capture attempt on 24 October 2026 failed and adds no hours. The 991,117 records are repeated observations of the same notices, not a million breakdowns.

An hour counts only if it lies between two consecutive usable captures no more than three hours apart, and the same substation appears at both ends with the same service and the same kind of problem. Longer gaps stay unobserved, so the result is not a safe lower bound: a notice can vanish and reappear between captures. Eligible intervals cover 69.9% of 2025 and 54.8% of 2026 up to the last capture.

Hot water and heating are counted separately and never added. Outages and below-standard supply can overlap. Two generic labels that mix different facilities (“complex comercial” and “p.d.”) are left out of rankings. 39 substations have no reliable position; they are in the search, without a dot on the map.

The 250-hour threshold is used as a reference point. A substation may serve several contracts, a notice may concern only some blocks, and compensation is calculated per contract from the company’s records. The 141 substations are not 141 contracts entitled to payment.

How much the result depends on the three-hour rule

Pick the longest gap allowed between two captures. At 24 hours the method also bridges long, unobserved gaps, so it is not the preferred estimate.

With gaps of at most 3 hours: 141 substations over 250 hours in 2025; captures cover 69.9% of the year.

Download the heat substation table (CSV)