Bucharest’s M6 metro to Otopeni Airport: station progress and tunnelling

Bucharest, Romania’s capital, is building a metro line to Henri Coandă International Airport at Otopeni. This scale drawing shows how much of each station’s structure Metrorex, the metro operator, has built, where it last reported the tunnel-boring machines, and which streets are restricted along the route.

Romania’s national road authority, CNAIR, lists the longest DN1 restrictions near Washington – Paris and Bruxelles through 27 July 2027. Most city-street diversions have no published end date.

The line, station by station

The tables below also show the stations, tunnel-boring machines and DN1 restrictions.

Select a station, a machine, an orange stretch of DN1 or a shaded area on a city street. Use “Play timeline” to follow the work month by month from April 2025.

November 2026

How much of each M6 station has been built?

Metrorex publishes a percentage for each station’s concrete structure, including its walls and slabs. Track, signals, station systems and trains are reported separately. The latest figures are for October 2026.

StationStructureProgress since June 2025What Metrorex reported for the latest month
Southern section 59% on Track 1 and 52% on Track 2October 2026Work on the junction with Line 4 continues, including relocating unforeseen utilities and building the structural elements.
Southern section 67%October 2026 break in seriesAll 523 plastic concrete piles and all 12 plastic concrete walls were completed. Over 52,600 cubic metres was excavated and over 32,700 cubic metres of concrete was poured.
Southern section 88%October 2026Over 51,400 cubic metres of concrete was poured.
Southern section 86%October 2026More than 36,200 cubic metres of concrete poured.
Southern section 81%October 2026More than 54,600 cubic metres were excavated and more than 23,200 cubic metres of concrete were poured.
Southern section 85%October 2026As part of the station’s architectural works, 72% of the concourse-level masonry was completed, including tie beams and small columns.
Southern section 78%October 2026Over 110,600 cubic metres of earth were excavated and over 49,500 cubic metres of concrete were poured.
Northern section 23%October 2026Diversion of the water and sewer networks continued, along with construction of the diaphragm walls.
Northern section 43%October 2026 break in seriesDiaphragm wall construction and excavation for the roof slab continued. Construction of the roof slab also began.
Northern section 34%October 2026 break in seriesExcavation for the roof slab in the station area was completed. Construction of the roof slab and columns continued, along with excavation at the lower levels.
Northern section 61%October 2026 break in seriesThe intermediate slab was completed, including its waterproofing. Top-down excavation at base slab level, placement of blinding concrete and base slab waterproofing continued.
Northern section 72%October 2026 break in seriesWork continued at the entrances, including on the external walls and the stair flight. Preparations also continued for casting the concrete that forms the falls on the roof slab.
Northern section 52%October 2026Excavation at intermediate level continued, along with reinforcement and casting of the intermediate slab, placement of blinding concrete and construction of the platform walls at base slab level.

1 Mai already serves line M4. These figures cover its connection to the M6. Metrorex reported the two tracks separately in August and September 2025 and again from June 2026. A faint line in the chart marks data from before a break in the series. How the percentages are reported.

How far have the tunnel-boring machines got?

Four tunnel-boring machines (TBMs) are assigned to the two parallel tunnels, one per track on each section. On the southern section, Sfânta Maria and Sfânta Ana set off from Tokyo towards 1 Mai in April and May 2025. On the northern section, Sfânta Parascheva left Bruxelles for Paris on 21 October 2026. Sfânta Ecaterina follows along Track 2.

Metres bored by each tunnel-boring machine since April 2025Sfânta Maria: 3,671 m on 8 October 2026. Sfânta Ana: 3,074 m on 31 October 2026. Sfânta Parascheva: 29.4 m on 31 October 2026.0 m1,000 m2,000 m3,000 m4,000 mApr 2025JulOctJan 2026AprJulOctAeroport BăneasaGara BăneasaPiața MontrealExpozițieiSfânta Maria · 3,671 mSfânta Ana · 3,074 mSfânta Parascheva · 29.4 m
Metres bored, from Metrorex announcements, station pages and monthly site diaries. A dot marks an arrival at a station. The largest gain between consecutive monthly reports was about 461 m, by Sfânta Maria in April 2026.

Sfânta Maria had bored 3,671 m of the 6.6 km of tunnel that Metrorex assigns it to 1 Mai. Boring pauses at each station so the machine can pass through the box and be serviced. Sfânta Maria reached Piața Montreal on 15 May 2026, cleared the station on 22 June and restarted its motors in late July.

The drawing uses the latest dated position from Metrorex announcements, station pages and site diaries. Between stations, the length bored gives an approximate position. Metrorex publishes no daily positions, so the drawing holds each machine at its last reported position until the next update.

Traffic restrictions and their end dates

Romania’s national road authority publishes a separate end date for each restriction on DN1 from Băneasa to the airport. For Bucharest’s city streets from 1 Mai to Băneasa, the details come from Metrorex notices, which only sometimes say how long a diversion will last.

Bucharest streets around the stations

These are the locations Metrorex listed in June 2026, with the latest notice for each site and its end date where one was given. Notices checked on 21 November 2026.

  1. 1 Mai Calea Griviței – Bd. Ion Mihalache

    The junction has been subject to restrictions since 24 August 2024. From Șoseaua Chitilei and Bd. Bucureștii Noi, the diversion runs along Carpați, Mircești and Caransebeș. Outbound traffic is diverted along Clăbucet, Aviator Popișteanu and Soveja towards Podul Constanța. The January 2025 notice also says that Carpați, Mircești and Caransebeș are closed between 22:00 and 06:00, except to local residents and public transport.

    No published end date. The last announced end date for the junction restrictions, 31 December 2024, has passed. The January 2025 notice said approval for the extension at 1 Mai was ‘in the process of being issued’ and gave no new date. In June 2026, the junction was still on the list of restrictions.

    Diversion notice, 14 August 2024Extension until 31 December 2024, 15 November 2024Overnight restrictions, approval pending, 23 January 2025Metrorex list of restrictions, 15 June 2026

  2. Expoziției – Piața Montreal Bd. Expoziției, până la str. Aviator Popișteanu

    Since 14 November 2025, traffic alongside the works has used a single lane towards Strada Aviator Popișteanu. Towards the tram 41 terminus, traffic has been reduced from two lanes to one. Access to Romexpo remains open.

    No published end date. The November 2025 notice gives no end date. The last published end date for the Pajura – Romexpo – Piața Presei Libere area, 30 September 2025, has passed.

    Stage III, one lane in each direction, 13 November 202530 September 2025 end date for Pajura – Romexpo – Piața Presei Libere, 23 January 2025Metrorex list of restrictions, 15 June 2026

  3. Piața Montreal Bd. Mărăști, la Pasajul Piața Presei Libere

    The latest detailed notice, dated 27 February 2025, set out two phases of restrictions on Bd. Mărăști. Two lanes were taken out of use in each phase, near the underpass exit and near the slip road above it, leaving one lane for each of the two traffic flows. Metrorex also announced restrictions in the underpass on the nights of 22 to 23 June and 2 to 3 July 2026.

    No published end date. The last announced approval was valid until 15 April 2025. In June 2026, Bd. Mărăști was still on the list of restrictions.

    Two-phase restrictions on Bd. Mărăști, 27 February 2025Underpass, night of 22 to 23 June, 19 June 2026Underpass, night of 2 to 3 July, 2 July 2026Metrorex list of restrictions, 15 June 2026

  4. Gara Băneasa Șos. București – Ploiești, la Fântâna Miorița

    Since the night of 14 to 15 October 2025 (Stage V), the works have occupied lanes 1 and 2 towards Piața Presei Libere, with two lanes open in each direction. Strada Tipografilor reopened with two lanes. On 26 February 2026, after the carriageway collapsed near the works, the Traffic Police imposed restrictions on Strada Tipografilor between the main road and Bd. Poligrafiei, and on lane 1 of the main road from Fântâna Miorița towards the Gara Băneasa STB stop.

    No published end date. The October 2025 notice no longer gives an end date. Earlier notices gave the expiry date of the approval, first 17 July and then 1 September 2025. The Traffic Police notice in February 2026 did not say how long the restrictions imposed after the ground collapse would last.

    Approval valid until 17 July 2025, 30 June 2025Phase IV, with approval valid until 1 September 2025, 6 August 2025Phase V, 14 October 2025Ground collapse near the construction site, with the Traffic Police notice reported by București FM, 26 February 2026Metrorex list of restrictions, 15 June 2026

  5. Aeroport Băneasa Bd. Aerogării – DN1 și str. Grațioasă

    Since 30 May 2026, the slip road from Bulevardul Aerogării to the DN1 has been closed. Traffic heading towards Otopeni uses a temporary two-lane slip road through the construction site near Strada Grațioasă. Two lanes are open on Bulevardul Aerogării towards Bulevardul Ion Ionescu de la Brad. Separately, Metrorex announced that Strada Grațioasă would be closed between the tram 5 terminus and the main road from 22 May 2024. The street was still listed as subject to restrictions in June 2026.

    Metrorex estimate: In May 2026, Metrorex estimated that the closure of the slip road from Bulevardul Aerogării would last about seven months from 30 May, taking it to around the end of December 2026. The notice gives no date for the usual route to reopen. No end date was published for the closure of Strada Grațioasă.

    Closure of Strada Grațioasă, 17 May 2024Aerogării slip road closed, 29 May 2026Metrorex list of restrictions, 15 June 2026

  6. Tokyo Str. Pană Buescu, la Băneasa Shopping City

    Since 24 April 2026, Strada Pană Buescu has been diverted before the roundabout under the overpass to make room for the pedestrian route to entrance B of Tokyo station, at the IKEA car park. The overpass slip road remains as it was. Metrorex announced that Strada Viorel Ciurea would be connected to the DN1 to provide another exit from the complex.

    Metrorex estimate: In April 2026, Metrorex estimated that the diversion would last about seven months from 24 April, taking it to around the end of November 2026. The notice gives no date for the usual route to reopen.

    Diversion of Strada Pană Buescu, 24 April 2026

DN1 restrictions in the national road register

Here are the dates CNAIR had listed for M6 work between Băneasa and the airport on 21 November 2026. The dates can change. A listing gives an administrative end date and does not confirm when the road will reopen.

  1. km 7+200–7+400 Aeroport Băneasa both directions

    Traffic runs in three lanes in each direction. The centreline of the national road has been shifted to the left to provide three 3 m lanes in each direction.

    Listed from 11 May 2026 through 31 December 2026

  2. km 7+700–7+950 Aeroport Băneasa towards Ploiești

    Traffic runs in two lanes from Bucharest towards Ploiești.

    Listed from 11 May 2026 through 31 December 2026

  3. km 8+300–8+450 Aeroport Băneasa towards Bucharest

    Traffic uses lane 2 of the DN1 slip road from Ploiești towards Bucharest.

    Listed from 11 May 2026 through 31 December 2026

  4. km 8+700–9+115 Tokyo towards Bucharest

    Traffic uses lane 2 of the DN1 slip road from Ploiești towards Bucharest.

    Listed from 11 May 2026 through 31 December 2026

  5. km 9+720–9+820 Washington

    Traffic uses the roundabout, with restrictions on the adjacent DN1 slip road. Traffic towards Ploiești is routed via Strada Liviu Librescu.

    Listed from 11 May 2026 through 31 December 2026

  6. km 10+200–10+500 Washington towards Bucharest

    Lane 1 of the DN1 from Otopeni towards Bucharest is being closed for kerb removal, road planing and resurfacing.

    Listed from 9 November 2026 through 22 November 2026

  7. km 10+200–11+450 Washington – Paris both directions

    Traffic runs in three lanes from Bucharest towards Ploiești and in two lanes from Ploiești towards Bucharest.

    Listed from 11 May 2026 through 27 July 2027

  8. km 12+400–13+050 Bruxelles both directions

    Traffic runs in three lanes from Bucharest towards Ploiești and in two lanes from Ploiești towards Bucharest.

    Listed from 11 May 2026 through 27 July 2027

  9. km 12+460–13+160 Bruxelles both directions

    Traffic runs in three lanes from Bucharest towards Ploiești and in two lanes from Ploiești towards Bucharest.

    Listed from 15 October 2026 through 27 July 2027

  10. km 14+185–14+345 Otopeni both directions

    Traffic runs in two lanes in each direction.

    Listed from 11 May 2026 through 31 December 2026

Latest Metrorex traffic notices

Two notices overlap at Aleea Privighetorilor (km 10+200–10+500). The 9 November notice closes lane 1 towards Bucharest for 14 days to widen the road. CNAIR lists it through 22 November. The 18 November notice closes lane 3 (the middle lane, in the notice’s wording) in both directions between 23:00 and 05:00 for 21 days, starting on the night of 17–18 November. It says all three lanes are open during the day. The notices leave it unclear how the restrictions overlap through 22 November. If the 21 days mean 21 consecutive nights, the last one ends at 05:00 on 8 December. The notice gives no final date.

When will the airport metro open?

Romania’s transport ministry gives 30 April 2029 as the contractual commissioning date. An opening date for passengers has yet to be announced. Officials have revised their public estimates several times.

  1. February 2025

    Metrorex estimated that structural work would finish in 2027 on the southern section and in 2028 on the northern section (Buletin de București, 17 February 2025).

  2. November 2025

    Metrorex director Mariana Miclăuș said the original target had been the end of 2027 and gave a new estimate of 2028 or early 2029 (Capital, 2 November 2025).

  3. March 2026

    The M6 train tender could be launched in the second half of 2026 at the earliest (Economedia, 4 March 2026). Passenger services need trains even if the tunnels are ready.

  4. April 2026

    A parliamentary question dated 6 April 2026 cited Metrorex figures from March 2026 putting completion of the structural work in the second quarter of 2029. The MP who asked the question estimated that passenger services could not start before 2030–2031.

  5. June 2026

    Romania’s Ministry of Transport gave 30 April 2029 as the contractual commissioning date for M6. That is when the contract for station fit-out, track and systems ends (reply to question 4757A, 11 June 2026).

  6. July 2026

    The same ministry listed three deadlines: 23 February 2028 for the southern structure, 30 April 2029 for the northern structure and 30 April 2029 for fit-out, track and systems. It identified unexpected underground concrete structures at station sites and between stations as a risk (reply to question 5398A, 9 July 2026).

  7. July 2026

    The latest progress report cited by News.ro (23 July 2026) put completion of the entire project on 9 November 2028, when it expected the last major diversion at Bruxelles station to end. It put completion of the station structures between March 2027 for Ion I.C. Brătianu and April 2028 for Paris.

  8. 2026

    Bucharest City Hall’s air quality plan assumes M6 is in service in 2029 (PICA București, rev. 2, p. 195). The city used the date for planning purposes.

For the history of the system and its other proposed lines, see The metro built against Moscow’s wishes.

What the percentages measure and how the drawing was made

Station percentages

Each station has a monthly entry on magistrala6.ro with a percentage for the structural work. In months without a figure, such as December 2025, when the station pages carried only an annual review, the drawing hatches the station and retains the last published value.

Some reported percentages fell without explanation. In February 2026, the northern section reported lower figures than in November 2025: Paris fell from 45% to 10%, Bruxelles fell from 38% to 5%, Otopeni fell from 55% to 32%, Ion I.C. Brătianu fell from 72% to 70%. The fact that the drops all appeared in the same month suggests that the way progress was calculated changed. The diagram breaks the lines at those points. There were two isolated drops as well: Pajura went from 52% in October 2025 to 45% in November 2025, and Ion I.C. Brătianu went from 78% in June 2026 to 71.5% in July 2026.

The percentages cover the structure alone. Station fit-out, track, electrical and mechanical equipment and low-voltage systems have a separate contract. It was signed on 26 March 2025, with work beginning on 1 September 2025 and a 44-month term. In May 2026 the transport ministry reported 3.78% for that contract, 69.08% for the southern structure and 27.11% for the northern structure. The construction diary put the same month at 68% in the south and 33% in the north.

Distances and positions

The route and stations come from OpenStreetMap. The mapped distances between stations differ from the lengths the machines reported boring. Measured against the reported lengths, the differences are −0.1%, −2.1%, −5.8%, −9.3%. The last comparison, for Sfânta Ana, also uses the distance Metrorex said remained. A machine’s position in the drawing follows the proportion it had bored of the distance between the two stations, based on its own readings. The depths of the stations and tunnels are schematic.

DN1 kilometre marks are tied to places Metrorex locates by the same markers: Aleea Privighetorilor (km 10+200–10+500), Bruxelles (km 12+760–12+970), Strada 23 August in Otopeni (km 13+493–14+345), and a slip road between Aeroport Băneasa and Tokyo (km 8+300–8+450). At Aleea Privighetorilor and Bruxelles, the two points used to align the drawing, the mapped position differs by 19 m from the midpoint of each published kilometre range. The other two points fall within their published ranges. This alignment applies north of Gara Băneasa, where DN1 runs alongside the metro line.

How often the figures change

Station percentages are published monthly, usually in the first half of the following month. Metrorex reports on the machines at each breakthrough and in the monthly site diary. Traffic restrictions can change at any time. The diagram and detail panels show the date of each layer.