Hospitals after the firesROEN

Romania · hospitals · public records to 15 November 2026

Fire safety in 28 Romanian hospitals: what became of the projects that missed the 2023 EU deadline

After fires in COVID wards at Piatra Neamț county hospital and the Matei Balș infectious-diseases institute in Bucharest, an EU-funded programme funded hospital projects for new electrical wiring, medical gases, ventilation, and fire and oxygen detectors. 22 projects, in 28 hospitals, were declared “non-functional”, the official term for projects not finished or not fully implemented by 31 December 2023, when the EU funding ended. The law requires them to be working by 31 December 2026; otherwise the beneficiaries can be made to pay the money back, in full or through financial corrections.

14 of 19works contracts signed in 2023: the term in the award notice, added to the signing date, runs past the EU deadline. For the other three projects no 2023 works contract appears.

2projects have continuations that, by their announced length, end in February 2027.

All 22 projects on one chart ↓

The works contracts were signed a few months before the deadline#

For 14 of these 19 contracts, the term in the award notice, added to the signing date, ends after 31 December 2023. For the eight contracts of the Bucharest hospitals administration (ASSMB), the notice gives the maximum: 195 days for design and construction, which reached January 2024. The calculation does not show the date by which the works had to, or did, finish. In Ineu the term was 11 months, to July 2024. In Moreni the contract was signed on 20 December 2023, 11 days before the deadline, for six months of work.

Each row is one project: the works contract and the term written into it, against the EU deadline
  • financing contract
  • tender launched
  • term of the works contract
  • the part after 31 December 2023
  • continuation with national money
  • works reported finished (year)
  • completion announced
  • end date announced, or calculated from the announced period, still ahead
202220232024202520262027EU deadline · 31.12.2023Legal deadline · 31.12.2026DorohoiFinancing contract: September 2022Works tender launched: 21 March 2023Works contract signed: 19 May 2023 · end calculated from the announced term: 31 December 2023Cantacuzino · BucharestFinancing contract: February 2022Works tender launched: 12 April 2023Works contract signed: 26 June 2023 · end calculated from the announced term: 7 January 2024Continuation contract: 15 May 2025Works reported finished in 2025Sfânta Maria · BucharestFinancing contract: February 2022Works tender launched: 12 April 2023Works contract signed: 26 June 2023 · end calculated from the announced term: 7 January 2024Continuation contract: 12 May 2025BeiușFinancing contract: July 2022Works tender launched: 29 March 2023Works contract signed: 28 June 2023 · end calculated from the announced term: 28 December 2023Obregia · BucharestFinancing contract: April 2022Works tender launched: 12 April 2023Works contract signed: 3 July 2023 · end calculated from the announced term: 14 January 2024Continuation contract: 9 May 2025completion announced: 7 September 2026Colentina · BucharestFinancing contract: February 2022Works tender launched: 12 April 2023Works contract signed: 4 July 2023 · end calculated from the announced term: 15 January 2024Continuation contract: 8 May 2025Works reported finished in 2025Victor Babeș · BucharestFinancing contract: February 2022Works tender launched: 25 April 2023Works contract signed: 10 July 2023 · end calculated from the announced term: 21 January 2024Continuation contract: 12 May 2025Works reported finished in 2025Malaxa · BucharestFinancing contract: March 2022Works tender launched: 12 April 2023Works contract signed: 12 July 2023 · end calculated from the announced term: 23 January 2024Continuation contract: 8 May 2025completion announced: 7 September 2026Sf. Ștefan, Colțea, Gomoiu · BucharestFinancing contract: February 2022Works tender launched: 25 April 2023Works contract signed: 12 July 2023 · end calculated from the announced term: 23 January 2024Continuation contract: 7 May 2025Works reported finished at two of three hospitalsCarol Davila · BucharestFinancing contract: February 2022Works tender launched: 25 April 2023Works contract signed: 14 July 2023 · end calculated from the announced term: 25 January 2024Continuation contract: 13 May 2025completion announced: 12 September 2026Hociotă (ENT) · BucharestFinancing contract: September 2022Works tender launched: 21 April 2023Works contract signed: 25 July 2023 · end calculated from the announced term: 25 December 2023completion announced: 19 February 2026IneuFinancing contract: August 2022Works tender launched: 29 May 2023Works contract signed: 24 August 2023 · end calculated from the announced term: 24 July 2024Miercurea-CiucFinancing contract: July 2022Works tender launched: 11 May 2023Works contract signed: 13 September 2023 · end calculated from the announced term: 13 April 2024AbrudFinancing contract: July 2022Works tender launched: 29 May 2023Works contract signed: 18 September 2023 · end calculated from the announced term: 18 February 2024Continuation contract: 30 April 2025end date announced, or calculated from the announced period, still ahead: 30 November 2026Cardiovascular Inst. · Târgu MureșFinancing contract: November 2022Works tender launched: 28 June 2023Works contract signed: 28 September 2023 · end calculated from the announced term: 1 December 2023completion announced: 27 April 2026Fundeni · BucharestFinancing contract: July 2022Works tender launched: 4 July 2023Works contract signed: 28 September 2023 · end calculated from the announced term: 28 March 2024OravițaFinancing contract: October 2022Works tender launched: 24 August 2023Works contract signed: 24 October 2023 · end calculated from the announced term: 24 February 2024PucioasaFinancing contract: September 2022Works tender launched: 11 September 2023Works contract signed: 29 November 2023 · end calculated from the announced term: 31 December 2023MoreniFinancing contract: July 2022Works tender launched: 5 September 2023Works contract signed: 20 December 2023 · end calculated from the announced term: 20 June 2024Continuation contract: 15 May 2025completion announced: 14 August 2026Oncology Institute · BucharestFinancing contract: September 2022Works tender launched: 28 April 2023Works contract signed: 27 April 2026 · end calculated from the announced term: 27 February 2027Continuation contract: 11 December 2025end date announced, or calculated from the announced period, still ahead: February 2027Sfântul Ioan · BucharestFinancing contract: August 2022no works contract in SEAP, 2023Railway hospitals · 5 townsFinancing contract: January 2023Continuation contract: 3 June 2025end date announced, or calculated from the announced period, still ahead: February 2027no works contract in SEAP, 2023’22’23’24’25’26’2731.12.202331.12.2026DorohoiFinancing contract: September 2022Works tender launched: 21 March 2023Works contract signed: 19 May 2023 · end calculated from the announced term: 31 December 2023Cantacuzino · BucharestFinancing contract: February 2022Works tender launched: 12 April 2023Works contract signed: 26 June 2023 · end calculated from the announced term: 7 January 2024Continuation contract: 15 May 2025Works reported finished in 2025Sfânta Maria · BucharestFinancing contract: February 2022Works tender launched: 12 April 2023Works contract signed: 26 June 2023 · end calculated from the announced term: 7 January 2024Continuation contract: 12 May 2025BeiușFinancing contract: July 2022Works tender launched: 29 March 2023Works contract signed: 28 June 2023 · end calculated from the announced term: 28 December 2023Obregia · BucharestFinancing contract: April 2022Works tender launched: 12 April 2023Works contract signed: 3 July 2023 · end calculated from the announced term: 14 January 2024Continuation contract: 9 May 2025completion announced: 7 September 2026Colentina · BucharestFinancing contract: February 2022Works tender launched: 12 April 2023Works contract signed: 4 July 2023 · end calculated from the announced term: 15 January 2024Continuation contract: 8 May 2025Works reported finished in 2025Victor Babeș · BucharestFinancing contract: February 2022Works tender launched: 25 April 2023Works contract signed: 10 July 2023 · end calculated from the announced term: 21 January 2024Continuation contract: 12 May 2025Works reported finished in 2025Malaxa · BucharestFinancing contract: March 2022Works tender launched: 12 April 2023Works contract signed: 12 July 2023 · end calculated from the announced term: 23 January 2024Continuation contract: 8 May 2025completion announced: 7 September 2026Sf. Ștefan, Colțea, Gomoiu · BucharestFinancing contract: February 2022Works tender launched: 25 April 2023Works contract signed: 12 July 2023 · end calculated from the announced term: 23 January 2024Continuation contract: 7 May 2025Works reported finished at two of three hospitalsCarol Davila · BucharestFinancing contract: February 2022Works tender launched: 25 April 2023Works contract signed: 14 July 2023 · end calculated from the announced term: 25 January 2024Continuation contract: 13 May 2025completion announced: 12 September 2026Hociotă (ENT) · BucharestFinancing contract: September 2022Works tender launched: 21 April 2023Works contract signed: 25 July 2023 · end calculated from the announced term: 25 December 2023completion announced: 19 February 2026IneuFinancing contract: August 2022Works tender launched: 29 May 2023Works contract signed: 24 August 2023 · end calculated from the announced term: 24 July 2024Miercurea-CiucFinancing contract: July 2022Works tender launched: 11 May 2023Works contract signed: 13 September 2023 · end calculated from the announced term: 13 April 2024AbrudFinancing contract: July 2022Works tender launched: 29 May 2023Works contract signed: 18 September 2023 · end calculated from the announced term: 18 February 2024Continuation contract: 30 April 2025end date announced, or calculated from the announced period, still ahead: 30 November 2026Cardiovascular Inst. · Târgu MureșFinancing contract: November 2022Works tender launched: 28 June 2023Works contract signed: 28 September 2023 · end calculated from the announced term: 1 December 2023completion announced: 27 April 2026Fundeni · BucharestFinancing contract: July 2022Works tender launched: 4 July 2023Works contract signed: 28 September 2023 · end calculated from the announced term: 28 March 2024OravițaFinancing contract: October 2022Works tender launched: 24 August 2023Works contract signed: 24 October 2023 · end calculated from the announced term: 24 February 2024PucioasaFinancing contract: September 2022Works tender launched: 11 September 2023Works contract signed: 29 November 2023 · end calculated from the announced term: 31 December 2023MoreniFinancing contract: July 2022Works tender launched: 5 September 2023Works contract signed: 20 December 2023 · end calculated from the announced term: 20 June 2024Continuation contract: 15 May 2025completion announced: 14 August 2026Oncology Institute · BucharestFinancing contract: September 2022Works tender launched: 28 April 2023Works contract signed: 27 April 2026 · end calculated from the announced term: 27 February 2027Continuation contract: 11 December 2025end date announced, or calculated from the announced period, still ahead: February 2027Sfântul Ioan · BucharestFinancing contract: August 2022Railway hospitals · 5 townsFinancing contract: January 2023Continuation contract: 3 June 2025end date announced, or calculated from the announced period, still ahead: February 2027

Rows are ordered by the date the works contract was signed. The term is the one in the award notice, counted from the day of signing; the bar stops at the calendar end date in the tender documents, where there is one.

The financing contracts were signed between February 2022 and January 2023. For the works contracts awarded in 2023, tenders were launched between 21 March 2023 and 11 September 2023, at the median about a year after the financing contract. Works contracts for 19 of the 22 projects were signed between 19 May 2023 and 20 December 2023. Half of them were signed 170 days or less before 31 December 2023.

For the other five contracts, the term in the notice or the limit in the tender documents ends no later than 31 December 2023, sometimes very soon after signing. In Pucioasa, for the contract signed on 29 November, the tender documents required the works to be finished by 15 December and accepted by 31 December. In Târgu Mureș, for the contract signed on 28 September, they required design and construction to be done by 1 December.

The term in an award notice is the one written into the tender documents. How long each job actually took is shown by the start order, suspensions and addenda in the signed contracts.

For three projects, no works contract awarded in 2023 appears in SEAP. At the Oncology Institute in Bucharest, the tender launched in April 2023 ended with a contract signed on 27 April 2026. At Sfântul Ioan hospital in Bucharest, three tenders started in 2023 were cancelled. The works at the five railway hospitals are paid for under a new contract signed in June 2025.

Who pays for the work after 2023#

After 31 December 2023 the works could no longer be paid for from the programme’s EU funds. An emergency ordinance from 2023 (OUG 36/2023) leaves those costs to the beneficiaries, from their own budgets or other lawful sources: the state budget for ministry hospitals, local budgets for those run by town halls and counties, which can also receive transfers from the state. In March 2024 the government created a National Programme for Investment in Hospital Infrastructure (PNIIUS), paid from the state budget through the Ministry of Investment and European Projects, which can take in hospital projects left unfinished at the end of 2023.

15 of the 22 projects got a continuation in this programme, under a new code. In Bucharest, ASSMB’s eight continuations have approved budgets of 62.35 million lei: 50.62 million from the programme and 11.73 million of its own money, according to the ASSMB report for 2025.

At ASSMB, the continuation money pays for the original project’s costs incurred after 1 January 2024, so it is not added to that project’s budget; elsewhere the continuation can also include new work. Invoices and claims can show how much was paid and from which sources, before and after 2023; the extra cost of the delay also needs a comparison with what the works would have cost on time.

Approved budgets for continuing the eight projects of the Bucharest hospitals administration (ASSMB), in million lei (ASSMB report for 2025)

from the national programmeown contribution

  1. Colentina12.08
  2. Sfânta Maria10.88
  3. Victor Babeș10.60
  4. Cantacuzino8.80
  5. Carol Davila7.18
  6. Sf. Ștefan, Colțea, Gomoiu5.98
  7. Obregia5.37
  8. Malaxa1.45

Other continuations, with the budget announced by the beneficiary

  • Railway hospitals38.07
  • Moreni9.37
  • Oncology Institute8.39
  • Fundeni4.54
  • Cardiovascular Inst.4.17
  • Abrud3.04
  • Hociotă (ENT)2.19

Budgets approved at the date of the report, not payments. They pay for the original projects’ costs incurred after 1 January 2024 and are not added to those budgets.

Seven projects with no continuation showing in the national programme#

For seven projects no new code appears in the national programme. Six belong to town halls or a county council: Miercurea-Ciuc, Ineu, Pucioasa, Dorohoi, Beiuș and Oravița. The seventh is Sfântul Ioan hospital in Bucharest, where the tenders were cancelled.

In Pucioasa, the town hall reported in September 2025 that 92% of the works were done and explained that the medical gases had to be installed after the thermal renovation of the same building, which was going on at the same time. In Miercurea-Ciuc, Harghita County’s technical director reported a long delay in July 2025 because the project had to be adapted to the fire service’s requirements. In Ineu, the mayor, quoted by the local press in June 2026, said the project had no funding.

For Dorohoi, Beiuș and Oravița no public statement of completion has been found. In January 2024 Beiuș town hall listed its project as under way; the Dorohoi hospital’s strategic plan mentions the project in 2025, without saying how far it has got.

What “finished” means in the hospitals’ own records#

For six projects the beneficiaries have announced completion: Malaxa, Carol Davila and Obregia in Bucharest, the Hociotă ENT institute, the cardiovascular institute in Târgu Mureș and the hospital in Moreni. For three more Bucharest hospitals, Cantacuzino, Victor Babeș and Colentina, ASSMB’s report for 2025 says the works were finished. In Abrud, completion was announced in October 2026, with 30 November 2026 as the project’s end date.

An announcement of completion is not an acceptance. The acceptance certificate and the commissioning tests document how each installation was accepted and tested; its state today needs further evidence. The law draws the same line: if a project is physically finished but not working, the managing authority recovers from the beneficiary the amounts owed to the European Commission for the corrections applied.

The Hociotă institute gives an example of a detailed record: it says what was finished before 31 December 2023 (medical gases and fire detection), what was done in 2024–2025 (intensive-care ventilation) and when the electrical system in the intensive-care area was accepted (June 2025).

Two continuations have announced periods that run past 31 December 2026#

OUG 36/2023 requires the projects on the non-functional list to be physically finished and working by 31 December 2026. The European Commission assesses their results by 15 February 2027. If a project is not fully implemented or has not met its objectives by 31 December 2026, the managing authority decides to terminate the financing contract and the beneficiary repays the EU money it received and the state co-financing, with any interest and penalties.

The Oncology Institute in Bucharest gives its continuation 14 months from the financing contract of 11 December 2025, which reaches February 2027. For its works contract, signed on 27 April 2026, the notice gives 10 months; counted from signing, that would also reach February 2027. The Transport Ministry gives the five railway hospitals 20 months from the contract of 3 June 2025, which also reaches February 2027.

The schedules alone do not prove a breach of the law: the legal deadline concerns the original project, and the continuation’s period may include administrative closure or work outside the original project. What must be working by 31 December 2026 is set out in the financing contracts and their addenda.

At the Fundeni institute, the continuation’s page gives 31 December 2025 as the completion date, yet the contract for fire detection and alarms was signed on 26 June 2026 and the one for cryogenic equipment on 9 October 2026.

The record for each project#

Each record shows what was funded, when the contracts were signed, the money with its date and type, what the latest public document says and the document that would clarify the rest.

Dorohoi · Project code 155558

Spitalul Municipal Dorohoi

Current state unknown

What was funded
Patient safety in the surgical and internal-medicine wards. Beneficiary: UAT municipiul Dorohoi.
What the latest document says
The design-and-build contract was signed on 19 May 2023, for eight months, with the term capped at 31 December 2023. The hospital’s strategic plan (2025 revision) mentions the project, without saying how far it has got.
The document that would clarify it
The acceptance certificate, if acceptance took place.

Timeline

  • Financing contractSeptember 2022
  • Works tender launched21 March 2023
  • Works contract signed19 May 2023 · term 8 months · end date in the tender documents 31 December 2023 · 226 days before the deadline

The money

  • Total budget, December 2023 register13,352,363.91 lei
  • Total budget, August 2025 register13,352,363.91 lei
  • EU payments, August 2025564,452.70 lei

Documents

Bucharest · Project code 152930

Spitalul Clinic Dr. Ion Cantacuzino

Works reported finished in 2025

What was funded
Electrical wiring, ventilation and air handling, medical gases, fire detectors and alarms for excess oxygen. Beneficiary: Administrația Spitalelor și Serviciilor Medicale București.
What the latest document says
ASSMB’s report for 2025 says the works were finished in 2025.
The document that would clarify it
The acceptance certificate and commissioning tests.

Timeline

  • Financing contractFebruary 2022
  • Works tender launched12 April 2023
  • Works contract signed26 June 2023 · term 195 days · 188 days before the deadline
  • Continuation contract15 May 2025 · new code 336803

The money

  • Total budget, December 2023 register12,642,424.34 lei
  • Total budget, August 2025 register12,642,424.34 lei
  • EU payments, August 20251,730,528.19 lei
  • Continuation budget (ASSMB, 2025)8,795,212.34 lei

Documents

Bucharest · Project code 152900

Spitalul Clinic Sfânta Maria

Current state unknown

What was funded
Electrical wiring, ventilation and air handling, medical gases, fire detectors and alarms for excess oxygen. Beneficiary: Administrația Spitalelor și Serviciilor Medicale București.
What the latest document says
ASSMB’s report for 2025 describes works and payments in 2025, contract extensions to 30 April 2026 and a final report sent for evaluation. The report contains no statement of completion.
The document that would clarify it
The acceptance of the finished works, after April 2026.

Timeline

  • Financing contractFebruary 2022
  • Works tender launched12 April 2023
  • Works contract signed26 June 2023 · term 195 days · 188 days before the deadline
  • Continuation contract12 May 2025 · new code 336770

The money

  • Total budget, December 2023 register14,171,825.40 lei
  • Total budget, August 2025 register14,171,825.40 lei
  • EU payments, August 2025892,245.00 lei
  • Continuation budget (ASSMB, 2025)10,882,226.53 lei

Documents

Beiuș · Project code 155566

Spitalul Municipal Episcop Nicolae Popovici Beiuș

Current state unknown

What was funded
Improving the existing infrastructure and fire safety. Beneficiary: Municipiul Beiuș.
What the latest document says
The design-and-build contract was signed on 28 June 2023, for six months. In January 2024 the town hall listed the project as under way, with its end date depending on an addendum.
The document that would clarify it
The addendum, the acceptance and the source of the money after 2023.

Timeline

  • Financing contractJuly 2022
  • Works tender launched29 March 2023
  • Works contract signed28 June 2023 · term 6 months · 186 days before the deadline

The money

  • Total budget, December 2023 register9,823,248.18 lei
  • Total budget, August 2025 register9,823,248.18 lei
  • EU payments, August 20256,394,639.37 lei

Documents

Bucharest · Project code 152980

Spitalul Clinic de Psihiatrie Prof. Dr. Alexandru Obregia

Completion announced by the beneficiary

What was funded
Electrical wiring, ventilation and air handling, medical gases, fire detectors and alarms for excess oxygen. Beneficiary: Administrația Spitalelor și Serviciilor Medicale București.
What the latest document says
ASSMB’s report for 2025 says the works were finished in 2025. For the continuation it announced completion on 7 September 2026, with a “value delivered” of 5,316,872.06 lei including VAT.
The document that would clarify it
The acceptance certificates and commissioning tests.

Timeline

  • Financing contractApril 2022
  • Works tender launched12 April 2023
  • Works contract signed3 July 2023 · term 195 days · 181 days before the deadline
  • Continuation contract9 May 2025 · new code 336806

The money

  • Total budget, December 2023 register7,940,014.27 lei
  • Total budget, August 2025 register7,940,014.27 lei
  • EU payments, August 20251,257,367.36 lei
  • Continuation budget (ASSMB, 2025)5,369,366.78 lei

Documents

Bucharest · Project code 152935

Spitalul Clinic Colentina

Works reported finished in 2025

What was funded
Electrical wiring, ventilation and air handling, medical gases, fire detectors and alarms for excess oxygen. Beneficiary: Administrația Spitalelor și Serviciilor Medicale București.
What the latest document says
ASSMB’s report for 2025 says the works were finished in 2025.
The document that would clarify it
The acceptance certificate and commissioning tests.

Timeline

  • Financing contractFebruary 2022
  • Works tender launched12 April 2023
  • Works contract signed4 July 2023 · term 195 days · 180 days before the deadline
  • Continuation contract8 May 2025 · new code 336772

The money

  • Total budget, December 2023 register16,619,508.94 lei
  • Total budget, August 2025 register16,619,508.94 lei
  • EU payments, August 20251,819,005.72 lei
  • Continuation budget (ASSMB, 2025)12,077,358.88 lei

Documents

Bucharest · Project code 152931

Spitalul Clinic de Boli Infecțioase și Tropicale Dr. Victor Babeș

Works reported finished in 2025

What was funded
Electrical wiring, ventilation and air handling, medical gases, fire detectors and alarms for excess oxygen. Beneficiary: Administrația Spitalelor și Serviciilor Medicale București.
What the latest document says
ASSMB’s report for 2025 says the works were finished in 2025.
The document that would clarify it
The acceptance certificate and commissioning tests.

Timeline

  • Financing contractFebruary 2022
  • Works tender launched25 April 2023
  • Works contract signed10 July 2023 · term 195 days · 174 days before the deadline
  • Continuation contract12 May 2025 · new code 336788

The money

  • Total budget, December 2023 register14,984,880.91 lei
  • Total budget, August 2025 register14,984,880.91 lei
  • EU payments, August 20251,732,579.63 lei
  • Continuation budget (ASSMB, 2025)10,602,102.27 lei

Documents

Bucharest · Project code 152646

Spitalul Clinic Nicolae Malaxa

Completion announced by the beneficiary

What was funded
Electrical wiring, ventilation and air handling, medical gases, fire detectors and alarms for excess oxygen. Beneficiary: Administrația Spitalelor și Serviciilor Medicale București.
What the latest document says
The August 2025 register lists the project as finished. For the 2025 continuation, the Bucharest hospitals administration (ASSMB) announced completion on 7 September 2026, with a “value delivered” of 1,291,698.40 lei including VAT.
The document that would clarify it
The acceptance certificates and commissioning tests for each installation.

Timeline

  • Financing contractMarch 2022
  • Works tender launched12 April 2023
  • Works contract signed12 July 2023 · term 195 days · 172 days before the deadline
  • Continuation contract8 May 2025 · new code 336614

The money

  • Total budget, December 2023 register12,547,889.93 lei
  • Total budget, August 2025 register12,547,889.93 lei
  • EU payments, August 20257,675,587.57 lei
  • Continuation budget (ASSMB, 2025)1,451,954.58 lei

Documents

Bucharest · Project code 152670

Sfântul Ștefan, Colțea and Victor Gomoiu hospitals

Works reported finished at two of three hospitals

Spitalul de Pneumoftiziologie Sfântul Ștefan, Spitalul Clinic Colțea, Spitalul Clinic de Copii Dr. Victor Gomoiu

What was funded
Electrical wiring, ventilation and air handling, medical gases, fire detectors and alarms for excess oxygen, in three hospitals. Beneficiary: Administrația Spitalelor și Serviciilor Medicale București.
What the latest document says
ASSMB’s report for 2025 says the works were finished at Sfântul Ștefan and Colțea. The Victor Gomoiu children’s hospital is not part of that statement. The 2023 works contract covers only Sfântul Ștefan and Colțea.
The document that would clarify it
What was done at the Victor Gomoiu hospital, under which contract and with what acceptance.

Timeline

  • Financing contractFebruary 2022
  • Works tender launched25 April 2023
  • Works contract signed12 July 2023 · term 195 days · 172 days before the deadline
  • Continuation contract7 May 2025 · new code 336561

The money

  • Total budget, December 2023 register9,392,135.31 lei
  • Total budget, August 2025 register9,392,135.31 lei
  • EU payments, August 20251,400,043.78 lei
  • Continuation budget (ASSMB, 2025)5,984,943.36 lei

Documents

Bucharest · Project code 152970

Spitalul Clinic de Nefrologie Dr. Carol Davila

Completion announced by the beneficiary

What was funded
Electrical wiring, ventilation and air handling, medical gases, fire detectors and alarms for excess oxygen. Beneficiary: Administrația Spitalelor și Serviciilor Medicale București.
What the latest document says
In September 2025 ASSMB reported the works finished. For the continuation it announced completion on 12 September 2026, with a “value delivered” of 6,493,697.08 lei including VAT.
The document that would clarify it
The acceptance certificates and commissioning tests.

Timeline

  • Financing contractFebruary 2022
  • Works tender launched25 April 2023
  • Works contract signed14 July 2023 · term 195 days · 170 days before the deadline
  • Continuation contract13 May 2025 · new code 336773

The money

  • Total budget, December 2023 register10,594,952.05 lei
  • Total budget, August 2025 register10,594,952.05 lei
  • EU payments, August 20251,534,541.77 lei
  • Continuation budget (ASSMB, 2025)7,182,364.23 lei

Documents

Bucharest · Project code 155431

Institutul de Fonoaudiologie și Chirurgie Funcțională ORL Prof. Dr. Dorin Hociotă

Completion announced by the beneficiary

What was funded
Medical gases, the electrical network and fire-safety systems. Beneficiary: Ministerul Sănătății.
What the latest document says
The institute says the medical gases and detection were done by 31 December 2023, intensive-care ventilation in 2024–2025, and the electrical system in the intensive-care area was accepted in June 2025. The continuation was announced as finished on 19 February 2026.
The document that would clarify it
The acceptance certificates for every component, not only for the intensive-care area.

Timeline

  • Financing contractSeptember 2022
  • Works tender launched21 April 2023
  • Works contract signed25 July 2023 · term 5 months · 159 days before the deadline

The money

  • Total budget, December 2023 register10,868,678.47 lei
  • Total budget, August 2025 register10,868,678.47 lei
  • EU payments, August 20257,735,897.06 lei
  • Continuation budget2,192,995.08 lei

Documents

Ineu · Project code 155359

Spitalul Orășenesc Ineu

Current state unknown

What was funded
Electrical systems, fire alarms and detection, the nurse-call system and medical gases. Beneficiary: UAT orașul Ineu.
What the latest document says
The design-and-build contract was signed on 24 August 2023, for 11 months. In June 2026 the mayor, quoted by the local press, said the project had no funding. No continuation under the national hospital programme appears.
The document that would clarify it
The state of the works and where the money for the rest will come from.

Timeline

  • Financing contractAugust 2022
  • Works tender launched29 May 2023
  • Works contract signed24 August 2023 · term 11 months · 129 days before the deadline

The money

  • Total budget, December 2023 register10,334,400.21 lei
  • Total budget, August 2025 register10,334,400.21 lei
  • EU payments, August 2025346,587.49 lei

Documents

Miercurea-Ciuc · Project code 154269

Spitalul Județean de Urgență Miercurea-Ciuc

Current state unknown

What was funded
Fire and excess-oxygen detectors, indoor electrical systems and medical gases at the county hospital. Beneficiary: UAT județul Harghita.
What the latest document says
In July 2025 the technical director of Harghita County Council reported a long delay because the project had to be adapted to the fire service’s (ISU) requirements. In September 2026 the county allocated 1.5 million lei from a loan to the investment’s ineligible costs, listing it among works in progress.
The document that would clarify it
The physical state of the works in November 2026 and the fire service approval for the renovated buildings.

Timeline

  • Financing contractJuly 2022
  • Works tender launched11 May 2023
  • Works contract signed13 September 2023 · term 7 months · 109 days before the deadline

The money

  • Total budget, December 2023 register14,935,942.57 lei
  • Total budget, August 2025 register14,935,942.56 lei
  • EU payments, August 20257,100,175.97 lei

Documents

Abrud · Project code 154294

Spitalul Orășenesc Abrud

Completion announced, with an end date of 30 November 2026

What was funded
Strengthening the hospital’s medical infrastructure for patient safety. Beneficiary: Orașul Abrud.
What the latest document says
Abrud town hall announced in October 2026 that the continuation was complete, giving 30 November 2026 as the project’s end date. The continuation budget rose by 1,400 lei compared with the 2025 announcement.
The document that would clarify it
The acceptance certificate, after 30 November 2026.

Timeline

  • Financing contractJuly 2022
  • Works tender launched29 May 2023
  • Works contract signed18 September 2023 · term 5 months · 104 days before the deadline
  • Continuation contract30 April 2025 · new code 337448

The money

  • Total budget, December 2023 register10,115,073.77 lei
  • Total budget, August 2025 register10,115,073.77 lei
  • EU payments, August 20256,690,088.78 lei
  • Continuation budget3,036,403.99 lei
  • Continuation budget3,037,803.99 lei

Documents

Târgu Mureș · Project code 155180

Institutul de Urgență pentru Boli Cardiovasculare și Transplant Târgu Mureș

Completion announced by the beneficiary

What was funded
The institute’s medical-gas infrastructure. Beneficiary: Ministerul Sănătății.
What the latest document says
The institute announced that the continuation was complete, giving 27 April 2026 as the end of implementation. The announcement came a few days before that date.
The document that would clarify it
The acceptance certificates and commissioning tests.

Timeline

  • Financing contractNovember 2022
  • Works tender launched28 June 2023
  • Works contract signed28 September 2023 · end date in the tender documents 1 December 2023 · 94 days before the deadline

The money

  • Total budget, December 2023 register10,178,693.20 lei
  • Total budget, August 2025 register10,178,693.20 lei
  • EU payments, August 20254,737,689.12 lei
  • Continuation budget4,170,804.04 lei

Documents

Bucharest · Project code 152882

Institutul Clinic Fundeni

Current state unknown

What was funded
The electrical network and fire-safety systems. Beneficiary: Ministerul Sănătății.
What the latest document says
The continuation also adds the liquid-nitrogen installation. Its official page gives 31 December 2025 as the completion date. The contract for fire detection and alarms was signed on 26 June 2026, and the one for cryogenic equipment on 9 October 2026.
The document that would clarify it
The amended schedule of the financing contract and the acceptance of the installations contracted in 2026.

Timeline

  • Financing contractJuly 2022
  • Works tender launched4 July 2023
  • Works contract signed28 September 2023 · term 6 months · 94 days before the deadline

The money

  • Total budget, December 2023 register10,515,041.82 lei
  • Total budget, August 2025 register10,515,041.82 lei
  • EU payments, August 20254,697,304.47 lei
  • Continuation budget4,544,320.70 lei

Documents

Oravița · Project code 155569

Spitalul Orășenesc Oravița

Current state unknown

What was funded
Modernising the town hospital. Beneficiary: Unitate administrativ-teritorială nivel local.
What the latest document says
The works contract was signed on 24 October 2023, for four months. No public statement of completion has been found.
The document that would clarify it
The acceptance certificate and the source of the money after 2023.

Timeline

  • Financing contractOctober 2022
  • Works tender launched24 August 2023
  • Works contract signed24 October 2023 · term 4 months · 68 days before the deadline

The money

  • Total budget, December 2023 register9,865,513.46 lei
  • Total budget, August 2025 register9,865,513.46 lei
  • EU payments, August 20256,517,209.47 lei

Documents

Pucioasa · Project code 155529

Spitalul Orășenesc Pucioasa

Current state unknown

What was funded
The medical-gas system. Beneficiary: Orașul Pucioasa.
What the latest document says
The contract was signed on 29 November 2023; the tender asked for the works by 15 December and acceptance by 31 December 2023. In September 2025 the town hall reported 92% of the works done and explained that the medical-gas installation was to be fitted after the thermal renovation of the same building.
The document that would clarify it
What the remaining 8% is, and the date of acceptance.

Timeline

  • Financing contractSeptember 2022
  • Works tender launched11 September 2023
  • Works contract signed29 November 2023 · term 4 months · end date in the tender documents 31 December 2023 · 32 days before the deadline

The money

  • Total budget, December 2023 register5,979,825.31 lei
  • Total budget, August 2025 register5,979,825.31 lei
  • EU payments, August 20254,898,873.11 lei

Documents

Moreni · Project code 155327

Spitalul Municipal Moreni

Completion announced by the beneficiary

What was funded
Electrical systems, medical gases, ventilation and fire detection in the surgical ward. Beneficiary: Municipiul Moreni.
What the latest document says
The works contract was signed on 20 December 2023, 11 days before the EU deadline, for six months of work. Moreni town hall announced completion of the continuation in August 2026, giving 14 August 2026 as the final date.
The document that would clarify it
The acceptance certificate and commissioning tests.

Timeline

  • Financing contractJuly 2022
  • Works tender launched5 September 2023
  • Works contract signed20 December 2023 · term 6 months · 11 days before the deadline
  • Continuation contract15 May 2025 · new code 336886

The money

  • Total budget, December 2023 register10,640,130.60 lei
  • Total budget, August 2025 register10,640,130.60 lei
  • EU payments, August 20251,268,242.71 lei
  • Continuation budget9,371,887.89 lei

Documents

Bucharest · Project code 152883

Institutul Oncologic Prof. Dr. Alexandru Trestioreanu București

Current state unknown

What was funded
The electrical network and fire-safety systems. Beneficiary: Ministerul Sănătății.
What the latest document says
The tender for the works began in April 2023; the contract was signed on 27 April 2026. The continuation, 8,392,672.81 lei from the state budget, covers oxygen sensors and medical gases and runs 14 months from the financing contract of 11 December 2025, which reaches February 2027.
The document that would clarify it
Which works from the original project must be working by 31 December 2026, and what is left for 2027.

Timeline

  • Financing contractSeptember 2022
  • Works tender launched28 April 2023
  • Works contract signed27 April 2026 · term 10 months
  • Continuation contract11 December 2025 · new code 351367

The money

  • Total budget, December 2023 register8,980,307.81 lei
  • Total budget, August 2025 register8,980,307.81 lei
  • EU payments, August 2025288,575.00 lei
  • Continuation budget8,392,672.81 lei

Documents

Bucharest · Project code 154610

Spitalul Clinic de Urgență Sf. Ioan București

Current state unknown

What was funded
Medical gases, the electrical network and fire-safety systems. Beneficiary: Ministerul Sănătății.
What the latest document says
Three tenders started in 2023 were cancelled. The result of the third was published on 15 September 2026. No continuation under the national hospital programme appears.
The document that would clarify it
Whether the works were done with other money and under which contract, or whether the project was dropped.

Timeline

  • Financing contractAugust 2022
  • Works contract signedNo works contract awarded in 2023 appears in SEAP.

The money

  • Total budget, December 2023 register10,128,887.98 lei
  • Total budget, August 2025 register10,128,887.98 lei
  • EU payments, August 2025421,382.45 lei

Documents

Iași, Drobeta-Turnu Severin, Galați, Cluj-Napoca, Simeria · Project code 155487

Five railway hospitals

Current state unknown

Spitalul Clinic Căi Ferate Iași, Spitalul General Căi Ferate Drobeta Turnu Severin, Spitalul General Căi Ferate Galați, Spitalul Clinic Căi Ferate Cluj-Napoca, Spitalul General Căi Ferate Simeria

What was funded
Electrical systems, medical gases, fire detection and ventilation in five railway hospitals. Beneficiary: Ministerul Transporturilor și Infrastructurii.
What the latest document says
The continuation, 38,073,077.10 lei, runs 20 months from the contract of 3 June 2025, which reaches February 2027. The December 2023 register gave the project a budget of 40,326,742.51 lei; the August 2025 register, 1,304,310.28 lei.
The document that would clarify it
What was done at each of the five hospitals, and what must be working by 31 December 2026.

Timeline

  • Financing contractJanuary 2023
  • Works contract signedNo works contract awarded in 2023 appears in SEAP.
  • Continuation contract3 June 2025 · new code 337910

The money

  • Total budget, December 2023 register40,326,742.51 lei
  • Total budget, August 2025 register1,304,310.28 lei
  • EU payments, August 2025993,781.28 lei
  • Continuation budget38,073,077.10 lei

Documents

Numbers that do not add up#

In the Investment Ministry’s August 2025 register, the 22 projects have total budgets of 235.92 million lei and EU payments of 70.70 million. The programme’s final report uses other measures and another currency: €55.59 million total cost and €12.54 million expenditure certified in the first stage. Payments, certified expenditure and approved budgets measure different things; the gap between them does not show money lost.

The December 2023 register gives Pucioasa EU payments of 18,674,463.34 lei, three times the project’s budget of 5,979,825.31 lei. The August 2025 register gives 4,898,873.11 lei.

The same contract can appear twice in the procurement register. In Miercurea-Ciuc the 2023 contract was published again in November 2026 with the same date and value; in Târgu Mureș, likewise, in 2025.

Method and limits#

The list of 22 projects is the annex to Order 1581/2026 of Romania’s Minister of Investment and European Projects, published in the Official Gazette no. 866 of 16 October 2026 (rows 36–57: the hospital projects of the REACT-EU axis of the Large Infrastructure Operational Programme, POIM). The annex lists the non-functional projects from the programme’s final report that include construction works subject to acceptance; it is not an inspection of the hospitals.

Budgets and payments come from the lists of contracted projects published by the ministry on data.gov.ro at 31 December 2023 and 31 August 2025; euro amounts from the annex to the final implementation report. Signing dates, terms and end dates of the works contracts come from the award notices in Romania’s electronic public procurement system (SEAP). For each project the main works contract signed in 2023 is shown; the term is the one in the notice, counted from the day of signing, and where the tender documents give a calendar end date the bar stops at that date.

Continuations come from ASSMB’s report for 2025 and from the beneficiaries’ announcements. The new code is matched to the old one by the pair of codes printed in the document or, where that is missing, by beneficiary, title and scope of works. The date of the financing contract is read from the ministry’s register; for some projects the register gives the date of registration, so the chart shows it to the month.

No amount is converted between lei and euros, and no amount is summed across years or across different kinds of budget. The page uses no hospital coordinates: the list is not a risk map and says nothing about any hospital’s safety today.

The programme’s failure at the 2023 deadline was documented by Mihaela Tănase for Context in March 2024. MonitorLegal explained the order containing the annex in October 2026.

The page’s data: hospitals-after-the-fires.csv (CSV, one row per project).

Sources#

  1. Official Gazette no. 866/16.10.2026, annex to Order 1581/2026 (MonitorLegal copy)
  2. Emergency ordinance 36/2023, consolidated, arts 11–14
  3. Emergency ordinance 29/2024 on the national hospital infrastructure programme
  4. Ministry of Investment, POIM contracted projects at 31 August 2025 (data.gov.ro)
  5. POIM final implementation report and annexes (archive)
  6. ASSMB, activity report for 2025, pp. 66–72 and 105–111
  7. ASSMB completion notices: Malaxa, Obregia, Carol Davila
  8. Bucharest Oncology Institute, PNIIUS project
  9. Transport Ministry, PNIIUS project 337910 announcement
  10. Fundeni Clinical Institute, type B fire-safety project
  11. Hociotă institute, projects
  12. SEAP award notices (e-licitatie.ro), read through sicap.ai
  13. Mihaela Tănase, Context, 11 March 2024
  14. MonitorLegal, Order 1581/2026 and the non-functional POIM projects