The place

The place
In 2008, a church was moved from the path of the mine
St Nicholas wooden church stood in the hamlet of Izvoru, near Valea Mare in Berbești. In 2008, expansion of the Panga lignite mine and the danger of landslides led to its dismantling and reassembly at a new site in the settled area. Archaeologists worked at the old site before the move.
The open pit and its spoil heaps were changing the landscape. The excavation report says expansion at Panga required the church’s removal and conservation. The town hall links the move to landslide danger and records damage to households in Valea Mare in 2008, 2009 and 2011.


The church
Timber, plaster and a stone foundation
The church had a rectangular nave, a narthex (pronaos) and a pentagonal altar. A bell tower rose above the narthex; a separate open porch stood on four carved wooden posts. Oak beams were covered with willow laths and plaster. The roof had once been clad in fir shingles.
The archaeologists also described later changes. In 1922, the church was plastered and painted in oil; the foundation was repaired with mortar containing more lime. After the 2008 move, the old oil painting was replaced with fresco, and the town hall records a change in the monument’s exterior appearance.

The dates
One inscription says 1423; the excavators concluded 1776
The excavation report transcribes a porch inscription recorded during the 1922 renovation: it says the church was built in 1423 and names renewals in 1863 and 1908. The panel now photographed above the entrance is a different one, painted after the 2008 move; it repeats earlier dates and adds the 2008–09 work.
The excavation report describes an interior inscription dated 1776 and a second inscription recording a foundation-laying in 1818–19. Its authors conclude that the church was built in 1776. The English summary on p. 90 compresses the evidence and gives 1818 as the construction year; the detailed Romanian discussion ties that date to a separate inscription.


The excavation
Four trenches surrounded and crossed the church
From 14 May to 28 June 2008, the team excavated a 39-metre exterior trench and three trenches inside the church. The longest, S II, followed the axis from the altar towards the entrance and measured 14 by one metre. Two side trenches were nine metres long; a two-by-two-metre test square checked the paving in front of the entrance. [1]
The 1.8-by-1.8-metre river-stone paving marked a route to a nearby space arranged for the feast-day meal and other occasions. Archaeologists also found nine large slabs in front of the entrance, which they attributed to the church’s construction. A door to the altar and small repairs showed that the building’s layout had changed over time.

The ground
A shallow foundation met a changing slope
The church stood on a hilltop with a 1.06-metre level difference from altar to porch and 0.26 metres north to south. Its foundation went only 20–30 centimetres below ground. The plinth was half a metre high at the porch and one metre at the altar, where the ground sat lower.
The trench showed river stones on the inside and cut limestone on the outside, bonded with mortar. The interior mortar contained more sand and little lime; an exterior repair later used more lime. The report describes two phases of intervention, one probably in 1922, when plastering and repairs were carried out.
The object
A brass spoon appeared inside, 40 cm down
In the excavation description, archaeologists place a brass spoon with incised floral motifs in S II, square 8, 40 centimetres below the walking surface. The report’s conclusion assigns it to S I instead; both passages give square 8 and a depth of 0.40 metres. It is the only portable find mentioned from the church excavation.
The authors report finding no pottery fragments. The report does not date the spoon, and its two trench references cannot be reconciled from the text: the description says S II, the conclusion S I. The square and depth agree, but the object cannot establish the church’s construction year on its own.

After the move
The church was repainted after relocation
The new fresco was painted in 2009 by Nicolae Sava with his daughter Irina. The church was reconsecrated in 2010. A photograph from that year shows the interior after oil painting was replaced by fresco; the inscription above the entrance records the move and recent interventions.
Today, the 2008 excavation report preserves a record of the old foundation and the objects found inside. Its authors date the building to 1776, while the entrance inscription claims 1423 and another panel records 1818–19. The sources preserve this difference; they do not provide one uncontested timeline.