Contracts for difference
A good-performance guarantee under a contract for difference can substitute for the authorisation guarantee for the beneficiary project's entire installed capacity.
ANRE framework exception · check the applicable textANRE / ENERGY / 2026
ANRE's 2026 materials place guarantees at three different moments: connection, capacity allocation and establishment authorisation. At 100 MW, two formulas produce €2 million and €3 million only in conditional scenarios. The third depends on the connection tariff. For developers, lenders and public-policy readers, the useful route is to check which stage and project class activates each formula.
ANRE · Romania · 21 May and 24 August 2026 · draft procedure, not a financial quote
Three gates are not three mandatory invoices. Each has a different base, timing and exceptions. This page separates verifiable figures from the amount we cannot calculate without a tariff and a project class.
Three units.
One total does not follow.
In ANRE's sources, the three values use incompatible units. One is a share of a tariff, one is an amount per MW requested for allocation, and one is an amount per installed kW. Adding them without conditions would hide the information a reader needs.
For the 100 MW example, this page shows formulas, not an invoice. The useful question is: which stage are you at, and which document triggers the guarantee?
Recalculate the example20% of the tariff excluding VAT in the relevant branches above 1 MW.
€20,000 for each MW of capacity requested in the 2026 procedure.
€30 for each installed kW, with exceptions and scope conditions.
A formula becomes relevant only after you know what is being requested, at which stage, and which project category applies.
The slider applies only the published formulas to a hypothetical capacity. It does not decide eligibility and it does not automatically add guarantees together.
The example uses whole MW. For authorisation, the formula converts MW to kW.
Order 16/2026 and the August draft procedure do not treat every project the same way. This is where the baseline rule meets the actual path.
A good-performance guarantee under a contract for difference can substitute for the authorisation guarantee for the beneficiary project's entire installed capacity.
ANRE framework exception · check the applicable textThe current Order treats repowering without increased power as an exception. Storage added at the same site appears in the August draft procedure, not as a final rule.
Do not extend the proposal to every battery or extensionThe authorisation guarantee follows completion and the reception record. The consulted procedure also describes updates for extensions.
A procedural obligation is not a delay estimateThe allocation participation guarantee has its own return point, while the 1% payment guarantee is separate. Do not treat either as the same guarantee that remains until reception.
Different stages · different guaranteesYou can check a formula's base. You cannot infer how much capital is committed, financing cost or one identical rule for every developer.
A guarantee may be constituted through a bank instrument, insurance or a transfer, depending on the applicable framework. The calculator figures are nominal and conditional. They are not money paid, executed or held at the same time.
CLAIM / LIMIT
We checked ANRE's May release, the 24 August consultation page and the official documents linked from it. The August order remains labelled as a draft.
The evidence sheet, formulas and archive hashes are in data/evidence.json. No individual data or instructions for a specific application are republished.