mariuscomper.ukRomână

ROMANIA’S ELECTRICITY · ONE REAL DAY, TWO EXPERIMENTS

The megawatt cemeteryWhy energy projects get stuck in Romania

On 1 September 2026, Romania had almost 115 GW of energy projects with grid-connection permits. Supplying a home depends on what gets built, where and when it produces. Follow a real day and explore what batteries can change.

Historical data

1 May 2025: from midday to evening demand

13:00–14:00

Midday: the battery can take some reported solar generation.

Demand4,217 MW
Reported solar1,067 MW
Net export209 MW
Historical OPCOM price-394.20 RON/MWh
MW · hourly means
DemandReported solar
8,0004,0000
Hourly means of 15-minute records: Fraunhofer ISE / Energy-Charts, using ENTSO-E data (CC BY 4.0). Solar is the output reported in this series; it does not capture all rooftop generation.
RON/MWh · historical priceHistorical data
9000−600
OPCOM prices for delivery on 30 April and 1 May 2025, aligned to Romanian time. Interval 15 in the 1 May report corresponds to 15:00–16:00 here.

It was a public holiday. Reported average demand was 4,217 MW at 13:00–14:00, rising to 6,447 MW at 21:00–22:00. Reported solar output fell from 1,067 MW to zero between those hours. Replay the day, then add an imaginary battery.

At 15:00–16:00, the price was −500.87 RON/MWh. At 21:00–22:00, it was 816.38 RON/MWh. A negative wholesale price does not automatically mean a negative bill at home.

Wholesale day-ahead price in RON/MWh. Your supplier’s charges, network fees and taxes are excluded. The imaginary battery does not change the historical price.

Battery experiment

How much midday energy could reach the evening?

Power (MW) limits how quickly a battery can charge or deliver; capacity (MWh) is the energy it can store. The hypothetical battery charges between 10:00 and 17:00 from part of the reported solar output and delivers after 18:00, subject to its power and stored energy. The dashed curve shows what other sources and exchanges would still need to supply.

Nominal duration
↑ One real day
Waiting0 MWhEnergy in battery at end of hour
Energy capacity0 MWh
MW · hourly means
Demand after solarWith imaginary battery
8,0004,0000

Assumptions: empty battery at the start; 90% round-trip efficiency; nominal duration means capacity divided by power, with losses reducing energy delivered; no simultaneous charging and discharging. Charging uses already reported generation. This experiment does not measure curtailed energy or predict prices, imports or local grid constraints.

The day, hour by hour

MW are hourly means; MWh measure energy. Positive exchanges mean net imports.

Interval start timeDemand (MW)Reported solar (MW)Reported generation (MW)Net physical exchange (MW)Historical OPCOM price (RON/MWh)
00:005,52403,682+1,593495.84
01:005,26803,571+1,492495.89
02:005,13703,511+1,415467.26
03:005,17603,502+1,437459.52
04:005,10703,470+1,452460.93
05:005,06903,476+1,416461.07
06:005,046133,549+1,318426.85
07:005,1611663,919+1,059407.98
08:005,1475364,437+528360.58
09:004,9078804,932−210278.41
10:004,6281,0504,781−3450.00
11:004,3431,0054,474−320-14.93
12:004,1461,0394,477−515-199.59
13:004,2171,0674,248−209-394.20
14:004,2799584,019+94-500.67
15:004,3738444,166+30-500.87
16:004,7056944,279+243-248.82
17:005,1394784,462+483-25.73
18:005,5073084,570+749187.23
19:005,836784,311+1,334485.10
20:006,24054,789+1,261640.72
21:006,44704,911+1,345816.38
22:006,02004,826+1,005602.51
23:005,51604,253+1,076498.07

Download hourly data (CSV)

ANRE · SEPTEMBER 2026

Almost 115 GW of projects, at different stages

On 1 September 2026, Romania’s energy regulator ANRE reported 1,643 renewable-generation projects with valid technical connection permits (ATR) and approved evacuation power of at least 1 MW: 114,966 MW in total. Of these, 1,045 had connection contracts (62,722 MW); 736 had both a connection contract and a building permit (39,281 MW); and 252 also had an ANRE establishment authorisation (15,362 MW). The report was published on 12 October. The 1 April snapshot had 1,500 projects and 86,332 MW: a difference of 28,634 MW of approved power, not evidence of power plants being built.

1,643projects with a valid ATR and at least 1 MW approved evacuation power
736with a connection contract and building permit
252with both documents and an ANRE establishment authorisation

These figures describe the documents and approved power reported on that date; they do not show which projects will be built or abandoned. The group with both documents is not the same as every project that has a building permit.

CONNECTION-RULE EXPERIMENT

What if the queue were reduced?

Explore a hypothetical scenario: removing some approved capacity outside the group with both documents. The slider sets an assumed capacity share; it is not a measurement for each project. ANRE’s report does not say what would be cancelled or give each project’s capacity.

0,0 GWHypothetically removed in this scenario
115.0 GWRemains of approved total

In this scenario, 0.0 GW are hypothetically removed and 115.0 GW remain from the 115.0 GW approved total.

The 75,685 MW outside the group of 736 projects with a contract and building permit do not tell us how many projects outside the group have building permits. ANRE’s totals do not identify which document each project is missing, what capacity would actually be released, or how much room the grid would gain. This is a national hypothetical, not measured available capacity or an ANRE forecast.

Where the electricity needs to travel

Projects also need a grid that can take their output. This schematic shows 31 substations at 400 and 220 kV, positioned at their towns, and approximate corridors. Select a station to identify it.

The map does not show station queues or available capacity: we have no verified local data for these. Equal dots identify stations, without ranking congestion.

HungarySerbiaBulgariaMoldovaUkraineBlack SeaPančevo (Serbia)Bălți (Republica Moldova)CernavodăMedgidia SudConstanța NordTariverdeIsacceaSmârdanGutinașSuceavaFocșani VestLacu SăratGura IalomițeiPelicanuStâlpuBucurești SudBraduDrăgănești-OltPorțile de FierIșalnițaReșițaTimișoaraAradMintiaSibiu SudAlba IuliaIernutGădălinRoșioriOradea SudBrașov
Outline: geoBoundaries, CC BY 4.0. Danube: Natural Earth, public domain. Positions mark towns; lines are not surveyed routes.

Northern links remain in preparation

Transelectrica, Romania’s transmission operator, described preparatory stages in its updates of 20–21 October 2026. Highlighting a route does not simulate commissioning it. Reșița–Pančevo has been in commercial operation since January 2025.

What we know and what we assume

The real day

Demand, generation and physical-flow series come from Energy-Charts, a Fraunhofer ISE service processing ENTSO-E data. We retained the 96 complete 15-minute intervals for 1 May 2025 in Europe/Bucharest and calculated hourly means. Net flow sums exchanges with neighbouring countries, with positive values for imports. Reported generation may differ from demand minus physical flows because the series have different definitions and adjustments.

The imaginary battery

Power is 0, 250, 500 or 1,000 MW; capacity in MWh is power multiplied by two or four hours. Efficiency is split equally between charging and discharging: √0.90 each way. Each hour, charging is limited by power, reported solar and remaining space. Discharging is limited by power, stored energy and demand remaining after solar. Local transmission constraints and other generators’ responses are ignored. Energy charged minus energy delivered equals losses plus energy left in storage.

The project queue

ANRE’s original report, published on 12 October 2026, gives the 1 September snapshot: 1,643 renewable-generation projects with valid ATRs and approved evacuation power of at least 1 MW, totalling 114,966 MW. Of these, 1,045 had connection contracts (62,722 MW), 736 also had building permits (39,281 MW), and 252 also had ANRE establishment authorisations (15,362 MW). The starting share is calculated directly as 39,281 / 114,966 and displayed as 34.2%. Hypothetical capacity removed = 114,966 × (1 − share in the group with both documents) × removal fraction. The report does not show how many projects outside that group have building permits; it does not measure capacity recoverable by the grid or allocate the total to substations. Primary sources are ANRE’s report and attached PDF.

The price and your bill

Prices are transcribed from OPCOM’s official reports for delivery on 30 April and 1 May 2025 in RON/MWh. Report interval 1 starts at 01:00 in Romania. We use interval 24 from the 30 April report for 00:00 on 1 May, followed by intervals 1–23 from the 1 May report. Historical prices remain unchanged under every battery setting. We calculate neither bill savings nor alternative market prices.

Sources and data

Download hourly data (CSV)