1960–1970
Ten years of building
Work began on 9 January 1960. In May 1964 the river was diverted, in October 1967 the power station started, and by mid-July 1970 the structure was complete. The Egyptian part of the reservoir is called Lake Nasser, the Sudanese part Lake Nubia. 1112
The reservoir full
169 km³: twice what the river brings in a year
The dam was designed for a maximum water level of 183 m, at which the reservoir holds 169 km³. The river brings a mean of 84.1 km³ a year, so the full reservoir is two years of water. Of the 169, Egypt's water ministry counts 31.6 for the silt that settles, 89.7 for the water that guarantees the flow from one year to the next, and 47.7 for holding back high floods. 115
At 180 m
At 180 m the whole reservoir holds 156.9 km³
An FAO table gives the reservoir's measurements at the 180 m level: 156.9 km³ of water and 6,216 km² for the whole reservoir, of which 132.5 km³ and 5,238 km² are the Egyptian part, Lake Nasser. Another table in the same document gives the whole reservoir 149.5 km³ at the same level. 12
The silt
Before the dam, the flood brought 110 million tons of silt a year
Before the dam, the annual flood deposited an estimated 110 million tons of silt a year, according to NASA. Now the silt is trapped behind the dam. NASA lists the consequences: fields need fertiliser, and where the river meets the Mediterranean there is erosion and saltwater intrusion. 13