Bucharest · 1952–2024

The metro they built without asking Moscow

In 1952, Soviet counsellors rejected the Bucharest metro as a “premature aspiration”. Twenty years later the Romanians designed and dug it on their own: 6 stations in November 1979, 64 today.

  • 1952the year Soviet counsellors rejected the project
  • 19 November 1979the first train with passengers, out of Ciurel depot
  • 78.7 km · 64 stationstoday's network, from the 2024 Metrorex report
Start with the refusal
SemănătoareaGrozăveștiEroilorIzvorPiața UniriiTimpuri Noi
The first six stations, in the order of the 19 November 1979 train: Semănătoarea, Grozăvești, Eroilor, Izvor, Piața Unirii, Timpuri Noi.

The refusal

First there was a no.

On the morning of 13 November 1952, the Central Committee plenum debates three projects: rebuilding the cities, the socialist remaking of Bucharest and — third on the list — building the metro. All three pass. But the metro still needed one more approval, from outside the room.

The scale of the project demanded, writes the historian of the Bucharest City Museum, “consulting the Soviet counsellors in order to get their approval”. The answer came back curt: the project was rejected, “a premature aspiration of the Bucharest regime”. The reasoning cited the groundwater lying close to the surface, the seismic zone and the buildings hit by the 1940 earthquake — problems that supposedly required solutions “impossible for the socialist camp”.

The Soviet condition said everything about what kind of metro that would have been: stations 20–40 metres deep, doubling as wartime shelters, on the Moscow model. A metro too expensive to be possible for Romania's 1952 economy. So the metro was postponed — on paper a pause, in fact a twenty-year wait.

The project was rejected, considered a premature aspiration of the Communist regime in Bucharest.

Cezar Petre Buiumaci, Urbanitas, 2020

The decision

Twenty years later, Bucharest no longer asks permission.

On 15 February 1972, in the meeting of the Executive Political Committee, Nicolae Ceaușescu decides on “naming a commission that would elaborate proposals concerning the development of public transportation in Bucharest, in particular by building transportation systems with electric means of great capacity and speed, as well as the construction of the subway”. Meanwhile the Titan–Balta Albă and Drumul Taberei–Militari estates had filled the city with people the trams could no longer hold.

The tone is set by the meeting of 17 January 1975, which approves the decree founding the Bucharest Metro enterprise. The transcript keeps Ceaușescu blunt: “I have seen the organisation problems, but I must tell you that everything has to be executed in the country, including the shields.” The shields — the machines that dig tunnels — were to be designed and cast in Romania.

Works start in April 1975, and the enterprise soon gathers specialists from railways, hydropower plants, mines and buried utilities — the people who already knew how to dig in Romania. But the deadlines are so tight that the design–prototype–test–redesign–series principle is simply abandoned: stages get “burned”.

The digging

Under Bucharest there is mud, water and pipes nobody has mapped.

The first buckets meet what everyone feared: muddy ground, heavy infiltration along the whole route. The soil had been investigated too little, and the shields — open-front, hand-dug — advanced through practically unknown ground, under old and vulnerable buildings, with too few skilled workers for such a job.

Groundwater remains the greatest problem: the strata change every few metres, and the pumps barely keep up. On one section the freezing of the groundwater is tried experimentally — an expensive, slow fix on a hurried site. Many techniques are applied “on the move”, against the clock, to catch the deadlines.

When outside help comes, it does not come from the East: Professor Herald Wagner, of the Hanover Technical University, visits the site and leaves one plain piece of advice — where hydrogeological studies are missing, drill probe boreholes and choose the fix case by case.

Line 1, in the builder's figures (Constantinescu et alii 1988, via Buiumaci):

4 million
cubic metres of earth dug out — about 1,600 Olympic pools
900,000
cubic metres of poured concrete
420,000
square metres of retaining walls
3,000 km
of power and telecom cables
40+
design and research institutes
45
collaborating enterprises

The number that says it all

12 metres

is the average depth of a Bucharest metro station. The Soviet school — the one that rejected the project in 1952 — demanded 20–40 metres: a shelter-metro, Moscow-style. Bucharest dug much shallower: 12 metres is about seven people standing head to toe; 40 metres would have been about twenty-four.

Average depth: metrorex.ro, via Buiumaci 2020. The 20–40 m demand: Udriște 2009, via Buiumaci.

The first train

19 November 1979: a train with people in it leaves Ciurel depot.

On 19 November 1979, the first metro train leaves Ciurel depot for Semănătoarea station, and the first passengers board from the platform. Three days earlier, on 16 November, the metro had been put into experimental service — with the public.

A whole month of trials with people in the cars follows — according to the Metrorex history, the only metro in the world tested this way. The official ribbon is cut on 19 December, and the reception report is signed on the 27th.

The first section measures 8.63 km and six stations: Semănătoarea, Grozăvești, Eroilor, Izvor, Piața Unirii, Timpuri Noi. The older history gives 8.1 km; 8.63 km is the length in the 2024 Metrorex report.

The map: station by station, year by year

Every dot is a station drawn at its real coordinates. Drag the years to watch the network grow.

Line

In 2023: 57 stations

The map: station by station, year by yearThe whole network, 1979–2023: 57 physical points, coloured by opening year.PantelimonRepublicaCostin GeorgianTitanNicolae GrigorescuDristorMihai BravuTimpuri NoiPiața UniriiIzvorEroilorGrozăveștiPetrache PoenaruCrângașiBasarabGara de NordPiața VictorieiȘtefan cel MareOborPiața IanculuiPiața MunciiTudor ArgheziBerceniDimitrie LeonidaApărătorii PatrieiPiața SuduluiConstantin BrâncoveanuEroii RevoluțieiTineretuluiUniversitatePiața RomanăAviatorilorAurel VlaicuPiperaPrecizieiPăciiGorjuluiLujeruluiPolitehnica1 Decembrie 1918Nicolae TecluAnghel SalignyGrivița1 MaiJiuluiParc BazilescuLaminoruluiStrăuleștiAcademia MilitarăOrizontFavoritTudor VladimirescuParc Drumul TabereiRomancierilorValea IalomițeiConstantin BrâncușiRâul Doamnei

The whole network, 1979–2023: 57 physical points, coloured by opening year.

The map shows 57 physical points; Metrorex counts 64 stations, because the shared Eroilor–Nicolae Grigorescu section counts on both lines, M1 and M3. The Dâmbovița is drawn from OpenStreetMap; the lines join the stations in route order.

Stations opened per decade (first openings):

1979
6
1980–1989
29
1990–1999
3
2000–2009
5
2010–2019
4
2020–2023
10

The network today

Five lines, 78.7 km of double track, 64 stations.

M1

km
31.01
stations
22
m journeys in 2024
62.0

M2

km
20.38
stations
15
m journeys in 2024
56.1

M3

km
22.20
stations
16
m journeys in 2024
21.8

M4

km
7.44
stations
8
m journeys in 2024
5.1

M5

km
7
stations
10
m journeys in 2024
7.0

M1 and M3 share 7 stations between Eroilor and Nicolae Grigorescu — which is why the per-line stations add up to 71 while the network counts 64.

The old station names (11)
  • Semănătoarea → Petrache Poenaru
  • Armata Poporului → Lujerului
  • Industriilor → Preciziei
  • Depoul IMGB → Berceni
  • IMGB → Dimitrie Leonida
  • Leontin Sălăjean → Nicolae Grigorescu
  • Pieptănari → Eroii Revoluției
  • Muncii → Costin Georgian
  • Policolor → Nicolae Teclu
  • Linia de Centură → Anghel Saligny
  • Laromet → Laminorului (project name)

Today's network, in journeys

152.0 million

metro journeys in 2024 — 6.5% more than in 2023. On average, about 400,000 a day; in normal conditions, about 500,000. A fifth of Bucharest's public-transport journeys, on a twentieth of the network's length. M1 and M2 alone carry 78% of the journeys.

Metrorex, activity report for 2024.

The driver's cab

You are driving the 19 November 1979 train. Six stations, six questions — bring them all in on time.

  1. Semănătoarea — The train leaves Ciurel depot for the first station. What was it called in 1979? Semănătoarea. Semănătoarea — it was named after the engineer Petrache Poenaru only in 2009.
  2. Grozăvești — How deep are the stations you are passing, on average? 12 metres. 12 metres — more than three times less than the 40 metres the Soviet school demanded.
  3. Eroilor — How long is the whole of today's section, to Timpuri Noi? 8.63 km. 8.63 km, per the 2024 Metrorex report. The older history gives 8.1 km.
  4. Izvor — In which year did the Soviet counsellors reject the metro project? 1952. 1952 — “a premature aspiration of the Bucharest regime”.
  5. Piața Unirii — “Everything has to be executed in the country, including…” — how does the January 1975 order end? the shields. “…including the shields” — the tunnelling machines, designed and cast in Romania.
  6. Timpuri Noi — End of the line. When was the metro's official ribbon cut? 19 December 1979. 19 December 1979 — the ribbon. The reception was signed on the 27th.

What is said and what the sources show

Five claims that go around, checked against documents.

False

“The metro opened on 16 December 1979.”

What is said. The date goes around in shorthand.

What the sources show. There were three moments: 16 November (experimental, with the public), 19 November (the first train out of Ciurel) and 19 December (the official ribbon). “16 December” mixes the first two with the third.

Limit. The source of the confusion: November versus December, in the same winter.

Imprecise

“The network is 80.1 km long.”

What is said. That is what the English Wikipedia says.

What the sources show. The 2024 Metrorex report gives 78.7 km of double track. The per-line lengths add up to 88.03 km, because the shared section is counted twice.

Limit. The differences come from rounding and from the shared sections.

Partly

“The first section was 8.1 km long.”

What is said. That is what the older Metrorex history gives.

What the sources show. The 2024 report gives 8.63 km for the same section. Both figures are attested; the one kept is 8.63 km, from the 2024 report.

Limit. Metrorex does not explain the 530-metre difference.

Attributed

“The only metro tested with people.”

What is said. A month of trials with passengers, between 16 November and 19 December 1979.

What the sources show. So the Metrorex history claims. The month of trials is documented; the worldwide uniqueness could not be verified independently.

Limit. Verified: the month of trials. Unverified: the uniqueness.

False

“The stations are deep, like Moscow's.”

What is said. A decades-old metro means palace-stations at great depth.

What the sources show. The average is 12 metres. Depths of 20–40 metres were the demand of the 1952 Soviet school — the very one that was rejected.

Limit. 12 metres is the network average, not the depth of every station.

Limits

What stays unresolved.

Sources

The political chronology and the digging figures come from Buiumaci 2020 (Urbanitas, Bucharest City Museum), citing Udriște 2009, Constantinescu et alii 1988, Ianuş 2015 and SANIC transcripts. The network, the sections and the journeys come from the Metrorex activity report for 2024. The month of trials with people comes from the Metrorex history reproduced by Evenimentul zilei (2014).

The station coordinates, the colours and the Dâmbovița come from OpenStreetMap (ODbL). The per-station years come from the station list (English Wikipedia), checked against the Metrorex sections. The derived figures (percentages, daily averages, Olympic pools) start from the numbers in the sources above.